High Court Kerala High Court

Sakthan Kuries And Loans Private … vs Sabu K.M. on 14 October, 2010

Kerala High Court
Sakthan Kuries And Loans Private … vs Sabu K.M. on 14 October, 2010
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

CRP.No. 150 of 2010()


1. SAKTHAN KURIES AND LOANS PRIVATE LTD.
                      ...  Petitioner

                        Vs



1. SABU K.M., AGED 49 YEARS, S/O.MANIAN,
                       ...       Respondent

2. PRASANNA KUMARI, AGED 42 YEARS,

                For Petitioner  :SRI.RANJITH XAVIER

                For Respondent  :SRI.B.S.SIVAJI

The Hon'ble MR. Justice THOMAS P.JOSEPH

 Dated :14/10/2010

 O R D E R
                             THOMAS P. JOSEPH, J.
                            --------------------------------------
                               C.R.P.No.150 of 2010
                            --------------------------------------
                   Dated this the 14th day of October, 2010.

                                         ORDER

This revision arises from the order dated December 12, 2008 on

I.A.No.6554 of 2008 in O.S.No.261 of 2005 of the court of learned Principal Sub

Judge, Thrissur. That is a suit for money filed by the petitioner based on an

alleged chitty transaction. Respondents/defendants appeared in court and filed

written statement taking up various contentions including that the suit is not

maintainable being premature. The case was posted for trial in the list on

17.12.2007. Respondents and counsel remained absent. Consequently, an

exparte decree was passed on 17.12.2007. On 05.09.2008 respondents filed

I.A.No.6554 of 2008 to set aside the exparte decree and I.A.No.6553 of 2008 to

condone the delay of 234 days in filing I.A.No.6554 of 2008. In the affidavit in

support of the application it is stated that respondents were out of station during

the relevant time and were not aware of the exparte decree. In connection with a

cheque allegedly issued by respondent No.2 in favour of petitioner according to

the petitioner in satisfaction of the exparte decree) the latter issued notice of

dishonour in preparation of preferring a complaint under Section 138 of the

Negotiable Instruments Act. Respondents contended that it is from that notice

that they learnt about the exparte decree. Petitioner preferred his objection to

CRP No.150/2010

2

both the applications on 20.10.2008. I.A.No.6553 of 2008 to condone the delay

came up before learned Sub Judge for consideration on 27.11.2008. Learned

Sub Judge passed the following order:

“Heard both sides. I.A. is allowed on payment

of cost of Rs.3,000/- within 15 days. Or else this

order stands as cancelled.”

Though respondents offered cost to the petitioner, the latter did not accept it.

Thereon respondents deposited cost in the court below. Noting that learned

Sub Judge disposed of I.A.No.6554 of 2008 as per order dated 12.12.2008 in

the following words:

“Delay condoned, on depositing cost. No

objection, I.A. is allowed. Call the suit on 19.1.2009.”

The order on I.A.No.6554 of 2008 is under challenge in this petition. Correctness

of the order on I.A.No.6553 of 2008 condoning delay is also challenged in this

revision. Learned counsel for petitioner contends that notwithstanding that

petitioner had preferred objection to the applications, learned Sub Judge has

proceeded as if there was no objection. It is contended that the impugned

orders are cryptic and there is no consideration of the explanation offered by

CRP No.150/2010

3

respondents for their absence on 17.12.2007. Learned counsel for respondents

contend that even if objection was preferred no such objection was pressed at

the time the matter was heard and accordingly learned Sub Judge passed the

impugned orders. It is pointed out by learned counsel that the suit is coming up

for trial on 15.10.2010.

2. No doubt, petitioner had preferred objections to the applications on

20.10.2008. I.A.Nos.6553 of 2008 and 6554 of 2008 came up before the

learned Sub Judge for hearing later. But it is seen from order dated November

27, 2008 on I.A.No.6553 of 2008 that it was after hearing both sides that

learned Sub Judge was inclined to condone the delay on terms of cost. There is

no reason to think that the objection preferred by petitioner was not before the

learned Sub Judge while the impugned order was passed. Learned Sub Judge

thought that having regard to the circumstances stated in the affidavit in support

of the application it is a case where delay has to be condoned on terms of cost

and accordingly delay was condoned on condition of payment of cost of

Rs.3,000/-. I do not forget that the learned Sub Judge has not passed a detailed

order on I.A.No.6553 of 2008. But, in the circumstances stated above, when the

learned Sub Judge has exercised discretion to allow the application on payment

CRP No.150/2010

4

of cost presumably because the learned Sub Judge thought that on the facts

and circumstances of the case respondents must be given an opportunity to

contest the case I do not find it necessary to interfere with that order.

3. Now turning to the order on I.A.No.6554 of 2008 learned Sub

Judge has observed that there was no objection in allowing the application.

There is no case for petitioner that counsel for petitioner was not heard when

I.A.No.6554 of 2008 was disposed of. In otherwords after hearing both sides

learned Sub Judge observed in the order dated December 12,2008 that there

was no objection. If that was wrong, remedy of petitioner was to seek review

before learned Sub Judge stating that it was not a case that petitioner had no

objection. That was not done. Apart from that, impugned orders are dated

27.11.2008 and 12.12.2008 and this petition itself is filed with a delay of 331

days (it is a different matter that the delay is condoned by a separate order). I

do not find it necessary to send back the case to the learned Sub Judge for

reconsideration for the reason that the impugned orders are passed in

November/December, 2008 and this revision is preferred on 15.03.2010 and

now suit itself is coming up for trial in the list on 15.10.2010. Allowing this

revision at this stage would disturb the schedule arranged by the learned Sub

CRP No.150/2010

5

Judge for trial and disposal of the suit. Parties can now contest the suit and get

a decision on merit. In these circumstances I do not find reason to interfere with

the impugned orders.

Resultantly this revision fails. It is dismissed.

I.A.No.717 of 2010 will stand dismissed.

THOMAS P.JOSEPH,
Judge.

cks