High Court Kerala High Court

Sam B.Sahayam vs L.R.Beena on 20 October, 2010

Kerala High Court
Sam B.Sahayam vs L.R.Beena on 20 October, 2010
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

RFA.No. 67 of 2005(E)


1. SAM B.SAHAYAM, S/O. BRUSE D.SAHAYAM,
                      ...  Petitioner

                        Vs



1. L.R.BEENA,
                       ...       Respondent

                For Petitioner  :SRI.G.SASIDHARAN CHEMPAZHANTHIYIL

                For Respondent  :SRI.RAM MOHAN.G.

The Hon'ble MR. Justice M.N.KRISHNAN

 Dated :20/10/2010

 O R D E R
                       M.N. KRISHNAN, J.
                   ...........................................
                R.F.A.Nos.67,165 & 166 OF 2005
                   .............................................
            Dated this the 20th day of October, 2010.

                          J U D G M E N T

R.F.A.No.67/2005 is preferred against the judgment

and decree of the 1st Additional Sub Judge, Trivandrum in

O.S.No.131/1995. R.F.A.No.165/2005 is preferred against

O.S.No.173/1995 and R.F.A.No.166/2005 is preferred against

O.S.No.175/1995. All these suits were for specific

performance of the contract with alternative reliefs for

damages and return of the amount.

2. The trial court on a consideration of the entire

materials held that the plaintiffs are not entitled to specific

performance of the contract, but directed the defendant to

return the advance amount paid + cost of construction made

by the plaintiffs in pursuance of the contract with 12%

interest from the last date of agreement dated 30.9.1994

till the date of suit and at the rate of 6% thereafter. It is

against those decisions, the defendant in these cases have

come up in appeal.

3. Heard the learned counsel for the appellant and also

: 2 :
R.F.A.Nos.67,165 & 166 OF 2005

the counsel for the respondent in RFA.No.67/2005.

O.S.No.131/1995 against which RFA.No.67/2005 contains

the following facts:

The plaintiff and defendant have entered into an

agreement for sale with respect to 16 cents of land

comprised in Sy.No.156/2-14 of Vilavoorkkal village on

14.12.1993 with the stipulation to pay Rs.8,300/= per

cent. The period of agreement was to expire on 31.1.1994.

An amount of Rs.5,000/= was paid as advance. Subsequently

as the defendant could not execute the document, by virtue

of the endorsement dated 29.1.1994 the period was

extended and ultimately on 31.3.1994 again the period was

extended up to 30.9.1994. While executing the second

agreement, it was agreed upon by the defendant that the

plaintiff can construct compound wall over the property to

be assigned. Now the amount claimed by the plaintiff, so far

as advance is concerned, is Rs.5,000/= + Rs.35,000/= as

cost of construction + difference in value on account of non

performance of the contract.

4. On the other hand, the defendant would contend

that he has not committed the breach. A suit was filed by

: 3 :
R.F.A.Nos.67,165 & 166 OF 2005

one Sara George and there was an injunction by the court

from executing the agreement and therefore, he was unable

to execute the document. It is also contended that the

plaintiff had only spent Rs.3,000/= towards construction

and therefore the plaintiff is not entitled to the relief.

5. A.S.No.173/1995 against which R.F.A.No.165/2005

is filed relates to the following facts:

There was an agreement between the plaintiff and the

defendant for the sale of 16 cents of property comprised in

Sy.No.156/2-14 of Vilavoorkkal village for a consideration of

Rs.9,000/= per cent and the period was to expire on

15.2.1994 and the plaintiff has paid an amount of Rs.5,000/=

as advance. On account of inability of the defendant the

agreement was initially extended up to 15.4.1994 and

thereafter again up to 30.9.1994. Meanwhile permission was

granted to the plaintiff to construct compound wall for the

property and for making other improvements. The plaintiff

had spent Rs.10,000/= for construction of the compound

wall. Though ultimately the plaintiff has sent a notice, the

defendant had failed to perform his part of the contract,

hence the suit. The defendant, on the other hand, would

: 4 :
R.F.A.Nos.67,165 & 166 OF 2005

contend that he had not committed the breach of contract.

Therefore the plaintiff is not entitled to any relief.

6. The suit O.S.No.175/1995 against which R.F.A.No.

166/2005 is filed contains the following facts:

Here also there was an agreement with respect to 15

cents of property on 14.12.1993 between the plaintiff and the

defendant with stipulation to pay at the rate of Rs.5,000/=

per cent and Rs.5,000/= was paid as advance. The

defendant did not perform his part of the contract. Therefore

there was a subsequent endorsement and an agreement

whereby the term was extended up to 30.9.1994 and in

pursuance to the agreement, the plaintiff has constructed

basement for compound wall and also dug a well and had

expended Rs.25,000/=. In spite of readiness and willingness,

the defendant did not comply with the terms of the contract

and hence the suit.

7. In the written statement the defendant would

contend regarding execution of the agreement but would

submit that he has not committed breach of the contract

and it had happened only on account of the suit filed by

Sara George against him. He would also contend that he is

: 5 :
R.F.A.Nos.67,165 & 166 OF 2005

prepared to pay the expense of Rs.15,000/= along with the

advance amount of Rs.5,000/=.

8. The cases were tried jointly and PWs 1 and 2 and

DW1 were examined. Exts.A1 to A18, B1, C1 and C2 were

marked and the court below granted a money decree in

favour of the plaintiff in all these cases. So far as specific

performance of the contract is concerned, this Court need

not probe into the matter for the reason that no appeal is

preferred by the plaintiffs challenging refusal of specific

performance of the contract. In all these cases there had

been an agreement between the plaintiff and the defendant

with respect to purchase of parcels of land and in all these

cases Rs.5,000/= had been paid as advance and by virtue of

the terms and conditions of the agreement, the plaintiff

had constructed compound wall and in one case had dug a

well. The court below found that the defendant was

restrained from performing his part of contract by virtue of

an order of injunction passed in a case filed by one Sara

George. The court considered that on account of the fact

that there was frustration of the contract the defendant

was unable to perform his part of the contract. I am not

: 6 :
R.F.A.Nos.67,165 & 166 OF 2005

saying anything on the same for the reason that now the

specific performance is negatived which is not challenged.

The plaintiffs would contend that they are entitled to

proportionate increase as damages on account of escalation

of price of the property which had been declined by the

trial court. That is also not the subject matter of these

appeals and therefore, it also does not require consideration.

9. The learned counsel for the appellant had raised the

following points before me namely: (1) since there was an

offer by the defendant to pay the advance amount with

some amount as damages for the construction of wall, the

defendant shall not be saddled with the liability of payment

of interest, (2) the agreement does not contain any specific

term with respect to payment of interest and (3) if at all

interest is to be paid, it has to be paid only on the excess

amount which is awarded by the court other than what is

offered by the defendant.

10. At the outset, I may like to point out that here is a

defendant who had entered into an agreement for sale of the

property with the respective plaintiffs without disclosing the

fact that at an earlier point of time he had entered into an

: 7 :
R.F.A.Nos.67,165 & 166 OF 2005

agreement for sale with one Sara George and the said

person had instituted the suit for specific performance of

the contract. So the conduct of the defendant by any

stretch of imagination cannot be said to be innocent. The

court passed an order of injunction. Necessarily it became

imperative for him to get the term of the agreement

extended and it was at that time the factum of litigation

and earlier agreement to sell have come into lime light.

Therefore all is not well with the conduct of the defendant.

11. The plaintiffs in these cases were earnest in getting

the property. They had paid the advance and at the request

of the defendant had agreed to extend the term of the

contract and further the defendant had permitted all these

plaintiffs to have the construction of the compound wall of

the property proposed to be purchased and they had invested

amount for the same. It is in this background one has to find

out the earnestness of the plaintiffs to get the property in

their favour. Just because the defendant submits that he is

prepared to pay the amount taken as advance and some

damages towards construction which the plaintiffs have

made, I am afraid that the same would entitle him to

: 8 :
R.F.A.Nos.67,165 & 166 OF 2005

contend for the position that he is not liable to pay the

interest. If he had such a good motive behind him, under

ordinary circumstance along with the written statement, he

would have deposited the amount admitted by him. So that

the court could have averted awarding interest with

respect to the amount that had deposited. The plaintiffs

cannot be blamed for not accepting that plea in the written

statement for the reason that they had filed the suit for

larger relief of specific performance of the contract.

12. Now regarding non mentioning of payment of

interest in the agreement. It has to be stated that under the

bonafide faith and belief they will become the owners of the

property, the plaintiffs had invested the amount for the

construction of the compound wall. Similarly they had

parted with Rs.5,000/= each for the purpose of purchase as

sale consideration. The amount of Rs.5,000/= has been

retained and enjoyed by the defendant whereas the

plaintiffs did not get any fruits from the said agreement. So

custody of Rs.5,000/= as far as advance amount is

concerned is to be repaid with interest. Similarly now a

situation has arisen whereby though the compound walls

: 9 :
R.F.A.Nos.67,165 & 166 OF 2005

are constructed, the plaintiffs are not entitled to get the

property for the reason of an order in another case. The

plaintiffs are not responsible for the same. They have never

contributed anything for the same. They were bonafide

persons prepared to purchase the property by spending

amount and they have invested the amount for the

construction of the compound wall and virtually they had

been thrown out of the property. They had invested their

amount which had become futile and did not get any benefit

from the same. It was on account of the conduct of the

defendant and it was a permissive construction made by the

plaintiffs and therefore, that amount also has to be

reimbursed.

13. Now it has to be stated that the wall remains in

tact in the property and it is only the amount that is spent

with interest has to be paid back. So far as estimation of cost

of the wall, I may state that it is not in a very satisfactory

manner the Commissioner has assessed. But it is a fact that

such a minimum amount should have been spent and

therefore I feel, the court after giving necessary deduction

only awarded a reasonable amount as the cost of

: 10 :
R.F.A.Nos.67,165 & 166 OF 2005

construction. The defendant has not filed any objection to

the Commissioner’s report and therefore he cannot take

shelter under non availability of data. So taking into

consideration these materials, I find that the court below has

proceeded in the matter in the correct perspective and only

had awarded reasonable amount to the plaintiffs in each

case with the stipulation to pay interest at 12% from the

date of agreement till the date of suit and thereafter at the

rate of 6% from the date of suit till realisation.

The judgment and decree of the trial court do not call

for any interference and therefore, all these appeals fail

and they are dismissed, but I direct the parties to bear their

respective costs.

M.N. KRISHNAN, JUDGE.

cl

: 11 :
R.F.A.Nos.67,165 & 166 OF 2005