High Court Kerala High Court

Save Citizen’S Forum vs State Of Kerala on 16 July, 2008

Kerala High Court
Save Citizen’S Forum vs State Of Kerala on 16 July, 2008
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C).No. 17115 of 2008(S)


1. SAVE CITIZEN'S FORUM
                      ...  Petitioner

                        Vs



1. STATE OF KERALA, REPRESENTED BY ITS
                       ...       Respondent

2. SECRETARY, IRRIGATION & WATER

3. KERALA WATER AUTHORITY, REPRESENTED

4. CHIEF ENGINEER, KERALA WATER AUTHORITY,

5. EXECUTIVE ENGINEER,

6. ASSISTANT EXECUTIVE ENGINEER,

7. UNION OF INDIA REPRESENTED BY ITS

                For Petitioner  :SRI.MOHAN JACOB GEORGE

                For Respondent  :SRI.P.PARAMESWARAN NAIR,ASST.SOLICITOR

The Hon'ble the Chief Justice MR.H.L.DATTU
The Hon'ble MR. Justice A.K.BASHEER

 Dated :16/07/2008

 O R D E R
                  H.L.Dattu, C.J. & A.K.Basheer, J.
                  ----------------------------------------------
                       W.P.(C).No.17115 of 2008-S
                  ----------------------------------------------
                   Dated, this the 16th day of July, 2008

                                JUDGMENT

H.L.Dattu,C.J.

The petitioner is a Society, registered under the provisions

of the Travancore-Cochin Literary, Scientific & Charitable Societies Act,

1955. The petitioner Society is formed by a group of public spirited

citizens in Peruvanthanam Village of Peermedu Taluk in Idukki District,

with the object of rendering assistance to the public in respect of their

common grievances and problems, to fight against anti-social activities, to

prevent corruption, etc.

2. It is the grievance of the petitioner in this petition filed

under Article 226 of the Constitution, that, the 3rd respondent, viz., Kerala

Water Authortiy, represented by its Managing Director, has not taken

effective steps in completing the Haileyburia Water Supply Scheme in

Idukki District.

3. The main prayer made in the writ petition is to direct the

respondents to complete the aforesaid water supply scheme in Idukki

District within the time limit prescribed, by monitoring the same till its

completion and commissioning.

W.P.(C).No.17115 of 2008

– 2 –

4. The Kerala Water Authority has filed its counter affidavit

before this Court. In that, at paragraph 4, they have stated the steps that

they have taken between 2001 and 2006 for redressal of the grievances of

the petitioner. Further, at paragraph 5, they have stated that due to the

delay in getting land from Tyford Estate, construction of Master Tank and

Booster Tank were delayed and there is some delay in completing the

project/scheme in question. In paragraph 6 of the counter affidavit, they

have stated that they are doing all their best to complete the scheme as

early as possible. It is also stated that they require another two years’ time

to complete the project/scheme. The affidavit filed by the respondents is

as under:

“5. Due to the delay in getting land from Tyford

Estate, construction of Master Tank and Booster Tank

were delayed. The estimate of pumping main are under

scrutiny at Chief Engineer’s (CR) Office, Kochi, except

Raw Water pumping main. The works related to Raw

Water Pumping main already tendered and tender

under scrutiny. The construction of Master Tank and 3

Nos. of Booster Tank were already tendered and the

tenders under scrutiny.

6. The petition argument is untrue. The project

work under this office are in good progress. We made

our best for the completion of the works. The officials

of Kerala Water Authority and the political parties are

very much interested for the completion of the scheme

W.P.(C).No.17115 of 2008

– 3 –

and expected to complete scheme within two years. But

due to unexpected reason, the completion of the

scheme delayed. The war foot steps are already taken

for the completion of the work in time by Kerala Water

Authority. No negligence has occurred from the

Government of Kerala as Kerala Water Authority for

the completion of the work. But some unexpected

reason, the work delayed.”

5. The main grievance of the petitioner, as we have already

stated, is that there is lethargic attitude on the part of the 3rd respondent in

completing the Haileyburia Water Supply Scheme in Idukki District. The

delay in completing the project is properly explained by the contesting

respondents. In our view, we need to only accept the explanation

offered. Since the contesting respondent, namely, Kerala Water

Authority, has undertaken before this Court that this project will be

completed as early as possible, it may not be necessary to continue to keep

this file on the board..

6. In view of the above, keeping in view the urgency of the

project canvassed by the petitioner-Society, in our opinion, if one year’s

time is granted from today to complete the project/scheme, it will not

cause any prejudice to the respondent – Kerala Water Authority.

Accordingly, we grant one year time from today to complete the

project/scheme.

W.P.(C).No.17115 of 2008

– 4 –

7. Accordingly, placing on record the affidavit of the third

respondent, we dispose of the writ petition.

Ordered accordingly.

H.L.Dattu
Chief Justice

A.K.Basheer
Judge
vku/dk.