High Court Kerala High Court

Shajan vs Joseph on 23 September, 2010

Kerala High Court
Shajan vs Joseph on 23 September, 2010
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

OP(C).No. 9 of 2010(O)


1. SHAJAN,S/O.JOSEPH,AGED 41,THOTTUPATTU
                      ...  Petitioner
2. RAJU JOHN,S/O.JOHN,AGED 41,THOYALIL
3. JOSHYA.CHEMPARATHY,S/O.AUGUSTINE,AGED

                        Vs



1. JOSEPH,S/O.ULAHANNAN,AGED 67,
                       ...       Respondent

2. PAILY,S/O.ULAHANNAN,AGED 73,

3. THOMMAN PAILY @RAJU,S/O.PAILY,AGED 40,

                For Petitioner  :SRI.K.JAYAKUMAR.K (SR.)

                For Respondent  : No Appearance

The Hon'ble MR. Justice THOMAS P.JOSEPH

 Dated :23/09/2010

 O R D E R
                   THOMAS P JOSEPH, J.

                  ----------------------------------------

                        O.P(C).No.9 of 2010

                   ---------------------------------------

             Dated this 27th day of September, 2010

                             JUDGMENT

Petitioners, pendente lite transferees have filed this

petition challenging Ext.P8, order by which learned Munsiff has

directed implementation of the order of mandatory injunction

passed on I.A.No.488 of 2007 with police assistance. Respondent

No.1 filed a suit for injunction against respondent Nos.2 and 3 for

enforcement of his right of way along plaint B schedule way to

the plaint A schedule belonging to them. Along with the

institution of suit, respondent No.1 filed application for

temporary injunction and an interim order of injunction was

passed restraining respondent Nos.2 and 3 from causing

obstruction to the user of the said pathway. Advocate

Commissioner inspected the property and submitted report

stating about existence of plaint B schedule pathway as pleaded

by respondent No.1. Later there was some attempt on the part of

respondent Nos.2 and 3 or somebody else on their behalf to

interfere with plaint B schedule pathway and thereon, respondent

No.1 filed I.A.No.488 of 2007 for an order of mandatory

injunction claiming that his only access to plaint A schedule is

O.P(C).No.9 of 2010
: 2 :

through plaint B schedule way and obstruction caused to it has

affected his access to plaint A schedule. Learned Munsiff allowed

that application. Accordingly, there was an order of mandatory

injunction directing respondent Nos.2 and 3 to restore the

pathway to its original position. Respondent Nos.2 and 3

challenged the order of prohibitory and mandatory injunction in

C.M.A.Nos.39 and 40 of 2007. Learned District Judge confirmed

the order of prohibitory injunction but directed that claim

regarding mandatory injunction can be decided along with the

suit. Respondent No.1 challenged that order in this court in

W.P.C.No.26789 of 2009 and this court by judgment dated

November 20, 2009 set aside the order of learned District Judge

and directed learned District Judge to consider C.M.A.No.39 of

2007 afresh. Learned District Judge considered the appeal and

confirmed the order passed by learned Munsiff on I.A.No.488 of

2007 (allowing mandatory injunction). That order became final.

Thereafter there was delay in learned Munsiff executing the

order on I.A.No.488 of 2007. Aggrieved, respondent No.1 filed

I.A.No.138 of 2010 for implementation of the order of mandatory

injunction on I.A.No.488 of 2007 and since respondent No.1

thought that the matter is being delayed he approached this

court with W.P.C.No.2144 of 2010. This court by judgment dated

O.P(C).No.9 of 2010
: 3 :

May 24, 2010 directed learned Munsiff to enforce the order of

mandatory injunction on I.A.No.488 of 2007. Since the Advocate

Commissioner reported that there was some obstruction by 3rd

parties in executing the order on I.A.No.488 of 2007, learned

Munsiff has issued Ext.P8, order to enforce the order of

mandatory injunction with the assistance of police. Petitioners

who purchased the property from respondent Nos.2 and 3

pendente lite filed applications for their impleadment in the suit,

to stay execution of order for restoration of the disputed pathway

and proposing that a road laid by them in connection with

development of the property purchased by them could be used by

respondent No.1 in settlement of his claim. Learned Munsiff has

allowed the application for impleadment but dismissed

I.A.No.1496 of 2010 for stay of operation of order on I.A.No.488

of 2007. Hence this writ petition. Learned Senior Advocate

appearing for petitioners contends that it was only on 07-09-2010

that petitioners were impleaded in the suit and they purchased

the property from respondent Nos.2 and 3 unaware of the

pending litigation or the right sought to be enforced by

respondent No.1 through plaint B schedule. Learned counsel has

produced documents to show that petitioners have developed the

property purchased by them from respondent Nos.2 and 3 and

O.P(C).No.9 of 2010
: 4 :

that in settlement of the claim made by respondent No.1, he

could be permitted to use the road that has been laid by them. It

is also contended by learned Senior Advocate that if the order of

mandatory injunction on I.A.No.488 of 2007 is to be enforced, it

would become necessary to dig up the property at a depth of

about 15 meters to mark out the pathway and that would involve

much hardship to the petitioner. In these circumstances learned

counsel prayed that Ext.P8, order passed by learned Munsiff on

I.A.No.138 of 2010 ordering police assistance for enforcement of

the order of mandatory injunction may be set aside and learned

Munsiff may be directed to pass appropriate orders on Ext.P9,

application where petitioners have made an alternative proposal

for the benefit of respondent No.1. A further prayer is that learned

Munsiff may be directed to enforce Section 89 of the Code of Civil

Procedure, 1908 (for short, “the Code”) for settlement of the

dispute. It is also prayed that in the meantime further proceedings

pursuant to Ext.P8, order may be kept in abeyance.

2. Learned counsel for respondent No.1 contends that

whatever that transpired at spot was with the knowledge of

petitioners and that petitioners cannot now wash off their hands

claiming that they were unaware of pendancy of litigation.

Learned counsel states that when W.P.(C).No.26789 of 2009 was

O.P(C).No.9 of 2010
: 5 :

pending in this court one of the petitioners had even taken part in

the mediation that took place at the mediation center of this court

which did not fructify. Petitioners have purchased the property

from respondent Nos.2 and 3 pendente lite, and hence petitioners

are not entitled to seek any relief as prayed for. It is also

contended that so far as enforcement of the order on I.A.No.488 of

2007 is concerned, that has become final by the judgment of this

court in W.P.(C).No.2144 of 2010 directing learned Munsiff to

enforce the stay order even before going for trial of the suit.

Learned counsel contends that at this stage there is no scope for

invoking Section 89 of the Code as requested by learned Senior

Advocate.

3. It is not in dispute that it is after the impugned orders

were passed that petitioners purchased property from respondent

Nos.2 and 3 through which disputed B schedule way existed. It is

not disputed that Advocate Commissioner inspected the property

immediately after institution of the suit and when he visited the

property a second time consequent to I.A.No.488 of 2007 he could

not find the said pathway. It follows that in the meantime the

pathway was interfere with either by respondent Nos.2 and 3 or,

somebody else on their behalf. It is in these circumstances that

learned Munsiff allowed I.A.No.488 of 2007 and that order has

O.P(C).No.9 of 2010
: 6 :

become final. The further fact which I have to bear in mind is that

as per report submitted by the Advocate Commissioner respondent

No.1 has no other means of access to the plaint A schedule except

plaint B schedule. Now the question is whether grievance of

petitioners is required to be redressed in this proceeding.

4. The Supreme Court in Marirudraiah and Ors. Vs. B.

Sarojamma and Ors. (2009(3) Supreme 309) has stated that

courts are not supposed to encourage pendente lite transactions

and regularise their conduct by showing equity in their favour. A

learned Single Judge of this court in Ananda Pai Vs. Gopala Pai

(2010(1) ILR Kerala 715) held that pendente lite transferee is

not entitled to get an order of injunction against the plaintiff and

that any such procedure is prima facie malafide. As I stated,

petitioners purchased the property from respondent Nos.2 and 3

admittedly after the order of temporary injunction was passed in

the case. If that be so, petitioners could very well see existence of

plaint B schedule way the Advocate Commissioner found at the

time of first inspection. Respondent No.1 states that one of

petitioners had taken part in the mediation that took place during

the pendancy of W.P.(C).No.26789 of 2010 in this court. I find no

reason why I should reject that assertion of learned counsel. If that

be so, it is idle for petitioners to contend that they were unaware of

O.P(C).No.9 of 2010
: 7 :

the pendancy of the suit or order of mandatory injunction whatever

be the assertion of respondent Nos.2 and 3 may have made in the

assignment deeds in favour of petitioners that there is no

encumbrance over the property. It follows that petitioners are

bound by the orders passed by the learned Munsiff pertaining to

plaint B schedule.

5. Then the next question is whether at this stage the

alternative way suggested by petitioners has to be accepted and

further proceedings for enforcement of the order on I.A.No.488 of

2007 is to be stayed. This court while disposing of

W.P.(C).No.26789 of 2010 has referred to the flagrant violation of

the order of prohibitory injunction indulged by respondent Nos.2

and 3 or his men whoever they may be. Paragraph 5 of the

judgment in W.P.(C).No.26789 of 2010 describes attempts made by

respondent Nos.2 and 3 or their men to violate the order of

temporary injunction. When there was delay in enforcement of the

order of mandatory injunction, this court by judgment in W.P.(C).

No.2144 of 2010 interfered and directed learned Munsiff to enforce

the order of injunction without waiting for trial of the suit.

6. A request is made to refer the dispute for arbitration

under to Section 89 of the Code. Respondent No.1 is not agreeable

to any such alternative mode of redressal of the dispute. The

O.P(C).No.9 of 2010
: 8 :

Supreme Court in V.K.Enterprises Vs. Shiva Steel (2010(3)

KLT S.N 75 – Case No.82) has stated that unless the parties to

the litigation assent, question of arbitration did not arise. On the

face of resentment of respondent No.1 to arbitration, no resort

could be had to Section 89 of the Code.

7. Then the next question is whether respondent No.1

should be asked to be satisfied with the alternative way suggested

by petitioners. Learned counsel for respondent No.1 states that

respondent No.1 is not agreeable for that course. He has obtained

favourable orders in this suit. In such a situation respondent No.1

could not be compelled to agree for the alternative way suggested

by the petitioners. In the circumstance the reliefs requested for by

petitioners cannot be allowed.

This petition fails. It is dismissed.

(THOMAS P JOSEPH, JUDGE)

Sbna/-