High Court Kerala High Court

Sibu Jacob vs K.S.E.B on 3 December, 2009

Kerala High Court
Sibu Jacob vs K.S.E.B on 3 December, 2009
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

OP.No. 32159 of 2001(C)



1. SIBU JACOB
                      ...  Petitioner

                        Vs

1. K.S.E.B
                       ...       Respondent

                For Petitioner  :SRI.R.SUDHIR

                For Respondent  :SRI.KODOTH SREEDHARAN, SC, KSEB

The Hon'ble MR. Justice S.SIRI JAGAN

 Dated :03/12/2009

 O R D E R
                          S. SIRI JAGAN, J
                ................................................
                     O.P. No. 32159 of 2001
               .................................................
         Dated this the 3rd day of December, 2009

                           J U D G M E N T

The petitioner is a consumer of electricity. On 7.8.2001, the

2nd respondent inspected the electrical installation at the

petitioner’s premises and prepared Ext.P1 Mahazar, wherein it was

stated that on examination of the meter in detail, which is a three

phase meter, the 1st and 3rd phases were working properly and the

2nd phase was found running in the reverse direction. Thereafter,

the petitioner was served with Ext.P2 notice claiming an amount of

Rs. 83,393/- which is described as a penalty charged as per the

inspection report of the 2nd respondent. The petitioner challenged

Ext.P2 bill before this court by filing O.P. No. 24313 of 2001. By

Ext.P3 judgment, this court relegated the petitioner to the remedy

by way of appeal before the Executive Engineer. Pursuant thereto,

the petitioner filed an appeal before the Executive Engineer, who

by Ext.P4 order rejected the contentions of the petitioner and

confirmed Ext.P2 bill. Thereafter, the petitioner was again served

with Exts.P6 and P7 bills demanding charges for the probable

energy consumed by the petitioner through the faulty meter, on the

O.P. No. 32159 of 2001 -2-

assumption that the meter was recording only /3 1 rdof the actual

consumption. The petitioner is challenging Exts.P2, P4, P5, P6 and

P7.

2. The primary contention of the petitioner is that the

respondents had no jurisdiction to decide the question as to

whether the meter was faulty and if the meter was faulty, the

energy charges payable by the consumer for the period in question.

According to the petitioner, that jurisdiction rests exclusively with

the Electrical Inspector under Section 26(6) of the Indian

Electricity Act, which was applicable at the relevant time and

without reference to the electrical inspector, respondents could not

have demanded and recovered energy charges on the assumption

that the meter was recording only 1/3 of the actual consumption.

rd

According to the petitioner, since the respondents have not chosen

to refer the dispute to the electrical inspector under Section 26(6),

going by the Division Bench decision of this court in Nirmala

Metal Industries v. K.S.E.B. [2006(3) KLT 465], the Board

cannot demand electricity charges for the alleged short recording

of electricity consumed by the alleged faulty meter. He also relies

on my decision in O.P. Nos. 26123, 27988 and 29518 of 1999, by

judgment dated 14.10.2008.

O.P. No. 32159 of 2001 -3-

3. The standing counsel for the electricity board contends

that in so far as the petitioner has not challenged Ext.P1 Mahazar,

it must be presumed that he has accepted the fact that the meter

was faulty and therefore there was nothing wrong in the

respondents demanding the electricity charges from the petitioner

on the ground that the meter was recording only /3 1 rd of the actual

consumption. The contention is that if the petitioner had a dispute

that the meter is actually correct, it was for him to raise that

dispute and seek reference under Section 26(6). The petitioner

having not done so, he cannot now dispute the correctness of the

demand made is the contention raised by the respondents.

Regarding Exts.P5 to P7 bills, the contention is that in order for the

petitioner to decide whether to seek reference under Section 26(6)

or not the respondents did not replace the meter for three months

and for that period also the electricity charges were demanded on

the basis that the meter was recording only /3 1 rd of the actual

consumption.

4. I have considered the rival contentions in detail.

5. In view of the pleadings before me, the question to be

decided is as to whether the bills issued by the respondents for

recovery of electricity charges without first resorting to reference

O.P. No. 32159 of 2001 -4-

under Section 26(6) of the Indian Electricity Act is valid or not.

Section 26(6) reads thus:

“Where any difference or dispute arises as to
whether any meter referred to in sub-section (1) is or is
not correct, the matter shall be decided, upon the
application of either party, by an Electrical Inspector; and
where the meter has, in the opinion of such Inspector
ceased to be correct, such Inspector shall estimate the
amount of the energy supplied to the consumer or the
electrical quantity contained in the supply, during such
time, not exceeding six months, as the meter shall not, in
the opinion of such Inspector, have been correct; but save
as aforesaid, the register of the meter shall, in the absence
of fraud, be conclusive proof of such amount or quantity:”

(underlining supplied)

6. As is clear from the first sentence of Section 26(6), in

order to attract jurisdiction of the Electrical Inspector under that

Section a difference or dispute as to whether any meter is or is not

correct should arise. The counsel for the petitioner would argue

that the word ‘arise’ means “come into being” or “come to notice or

action as a result of” as given in Oxford Dictionary. According to

him, word ‘arise’ should be considered in contradistinction with

‘raised’. Therefore, according to him as soon as a meter is found

faulty a dispute arises and therefore electricity board is bound to

refer that dispute under Section 26(6) to the Electrical Inspector. I

am unable to agree. If that be so, in every case, where the meter is

found faulty, automatically the electricity board would be bound to

O.P. No. 32159 of 2001 -5-

refer the matter to the Electrical Inspector. That is not what is

contemplated under Section 26(6). A dispute or difference would

arise only when one party asserts the existence or non-existence of

a fact and the other party disputes the existence or non-existence

of that fact. When one person asserts the existence or non

existence of a fact and the other party does not dispute the same

there arises no difference or dispute. Therefore, going by the

reasoning given by the counsel for the petitioner himself only if a

difference or dispute arises the jurisdiction of the electrical

inspector attracted. That is the law declared by the Supreme Court

in Tata Hydro-Electric Power Supply Co. Ltd. v. Union of

India [AIR 2003 SC 1581], wherein in paragraph 15 it is held thus:

“It was urged before the High Court as also before
us that having regard to the judgment of this Court in
U.P.S.E.B. v. Atma Steel (supra) it is no longer open to
the appellant to contend that CT was not an apparatus
within the meaning of Section 26(7) of the Act. Having
perused the judgment of this Court in Atma Steel’s case
(supra), we also entertain no doubt that CT is an
apparatus within the meaning of Section 26(7) of the
Act.”

7. Here, in Ext.P1 Mahazar it is specifically stated that on

detailed inspection it was found that one phase of the three phase

meter was running in reverse direction. It does not need any

expertise to understand from the same that what it means is that

O.P. No. 32159 of 2001 -6-

the meter is faulty. Therefore as soon as Ext.P1 is received the

petitioner must have known that according to the respondents the

meter is faulty. If the petitioner had a case that the meter is not

faulty he should have contested Ext.P1 immediately on receipt of

the same. Only if he had done so, a difference or dispute would

arise as to whether the meter is or is not correct. It is also

pertinent to note that in Ext.P8 memorandum of writ petition in

W.P(C) No. 24313/2001, which the petitioner has produced along

with I.A. No. 15257 of 2009, the petitioner did not choose to

challenge Ext.P1 although he had produced Ext.P1 in that writ

petition also. In fact in Ext.P9 appeal filed by the petitioner as

directed in Ext.P3 judgment, there is no assertion that the meter is

not faulty nor is there a demand for reference of the any dispute

under Section 26(6). The explanation of the petitioner for this is

that at that time the petitioner was not aware that Ext.P2 demand

was for deficit current charges for the past six months on account

of the fault in the meter, since Ext.P2 specifically stated that

demand is for penalty. It is prepared that in Ext.P2 the

respondents have chosen to describe the demand as penalty

charged as per the inspection report. Even then the petitioner

cannot dispute the fact that going by Ext.P1 it is abundantly clear

O.P. No. 32159 of 2001 -7-

that according to the respondents the meter was faulty. Therefore

if the petitioner had a contention that the meter was not faulty the

petitioner was bound to raise that dispute, when only the dispute

would arise as contemplated under Section 26(6) of the Indian

Electricity Act. Therefore in my opinion since the petitioner

condescended to the fact that the meter was faulty, the

respondents were not bound to refer any dispute for decision of the

electrical inspector as required under Section 26(6).

8. Then the only the question is whether the petitioner is

liable to pay the amount demanded by the respondents on account

of the defect in the meter. Nowhere has the petitioner disputed

the specific statement in Ext.P1 that one of the phases of the power

meter was running in the reverse direction. That being so, it is

clear that the meter was recording only /3 of the consumption. In
1 rd

such circumstances, the respondents are justified and demanding

the electricity charges for the balance /32 rd consumption for six

months prior to the date of detection of the defect in the meter.

Therefore I do not find any merit in the challenge against Exts.P2

and P4.

9. But after having found the meter to be faulty it is not

proper on the part of the respondents to continue billing the

O.P. No. 32159 of 2001 -8-

petitioner by a calculator on the basis of the reading in the faulty

meter. The maximum they could have done is to charge the

petitioner for the average consumption per month as per the

reading in the replaced meter. Accordingly Exts.P5 to P7 bills are

quashed. The respondents are directed to issue fresh bills in the

place of Ext.P6 to P7 on the basis of the average consumption of

the petitioner for three months subsequent to the replacement of

the meter.

The writ petition is disposed of as above.

sd/-

S. SIRI JAGAN, JUDGE
rhs

// True copy //

PA to Judge