High Court Kerala High Court

T.I.Sali vs Chief Engineer on 26 February, 2009

Kerala High Court
T.I.Sali vs Chief Engineer on 26 February, 2009
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

OP.No. 12524 of 2001(N)



1. T.I.SALI
                      ...  Petitioner

                        Vs

1. CHIEF ENGINEER, P.W.D., TRIVANDRUM
                       ...       Respondent

                For Petitioner  :SRI.C.UNNIKRISHNAN (KOLLAM)

                For Respondent  :GOVERNMENT PLEADER

The Hon'ble MR. Justice S.SIRI JAGAN

 Dated :26/02/2009

 O R D E R
                             S. Siri Jagan, J.
               =-=-=-=-=-=-=-=--=-=-=-=-=-=-=-=-=-=
                       O.P. No. 12524 of 2001
               =-=-=-=-=-=-=-=-=--=-=-=-=-=-=-=-=-=
                Dated this, the 26th   February, 2009.

                           J U D G M E N T

Disciplinary proceedings were initiated against the petitioner

in respect of payment of bill amount to a contractor for maintenance

of a pond in Mulakkulam Panchayat under the drought relief scheme,

while he was working as an Assistant Engineer at Kaduthuruthy Block

of the Public Works Department of the Government of Kerala. The

estimate amount was Rs. 12,500/-. Administrative and technical

sanction was also granted for that amount. The work was completed

on 26-5-1987. Measurement was recorded in the M Book by the

overseer and it was check-measured by the petitioner on 26-5-1987

itself. Pursuant thereto, an amount of Rs. 12,164.70 was paid to the

contractor, who was the convenor of a beneficiary committee who

undertook the work. Subsequently, one of the members of the

beneficiary committee filed Ext. P1 complaint alleging that the work

was not completed and the man days calculated was exaggerated.

The B.D.O concerned forwarded Ext. P1(a) report to the Collector

stating that the allegation regarding the excess man-days is not true.

In respect of the other allegation, the report was silent. By Ext. P2

dated 31-12-1987, the petitioner and the overseer were placed under

suspension. Thereafter, it appears that the Executive Engineer of

PWD Roads Division, Kottayam was directed to conduct an enquiry.

By Ext. P3 dated 24-12-1988, the Chief Engineer forwarded Ext. P3

report of the Executive Engineer to the Government. Earlier, the

Chief Technical Examiner had measured the pond as 47 meters x 20.4

meters whereas in Ext. P3 report the size of the pond was measured

as 62 meters x 28 meters. The Executive Engineer also said that in

view of passage of time and from the available quantity of the cut

soil, the correct quantity of the work done cannot be arrived at, at

that point of time. Subsequently, Ext. P4 charge memo dated 6-6-

O.P. No. 12524/2001 -: 2 :-

1989 was issued to the petitioner directing him to submit his written

statement of defence against the charges levelled in Ext. P4 with a

proposal to recover the proportionate share of loss sustained by the

Government out of the excess amount of Rs.7165/- paid to the

contractor, from the petitioner. A statement of allegations was

attached to the same. The petitioner filed Ext. P5 reply refuting the

allegations against the petitioner, specifically pointing out that in Ext.

P3 report of the Executive Engineer, no finding against the petitioner

was recorded. However, by Ext. P6 show cause notice, the

petitioner’s written statement of defence was rejected and it was

found that the petitioner is responsible for excess payment of

Rs.7165/- made to the contractor. He was directed to show cause why

the punishment of recovery of the said amount should not be imposed

on him. The petitioner filed Ext. P7 objections, However, by Ext. P8

order, the same was confirmed and it was directed to recover an

amount of Rs.2866/- in 22 instalments of Rs.125/- each from his

salary with the last instalment as Rs. 116/- . The petitioner filed Ext.

P9 appeal to the Government on 15-11-1990. After two years, by Ext.

P10 dated 25-8-1992, the petitioner was directed to show cause why

the punishment should not be enhanced and the punishment of

barring of increments for two years with cumulative effect should not

be imposed on the petitioner in addition to the recovery of loss.

Again, the petitioner submitted Ext. P11 objection. Thereafter,

according to the petitioner, he was not informed of any further orders

pursuant to Ext. P10.

2. While so, by Ext. P12, the Chief Engineer sanctioned 10 year

higher grade to the petitioner excluding the period of suspension

undergone by him apparently because the period of suspension had

not been regularised. When Ext. P12 dated 21-10-2000 was

O.P. No. 12524/2001 -: 3 :-

forwarded to the Accountant General, the Accountant General said

that by order dated 23-5-1996, the period of suspension of the

petitioner had already been regularised. According to the petitioner,

it was from Ext. P13 he came to understand about the order dated 23-

5-1996, which apparently was on the show cause notice for enhancing

the punishment. Therefore, he obtained copy of that order, which is

produced as Ext. P14. In Ext. P14, in addition to the recovery of an

amount of Rs.2868/- the punishment of barring of increments for two

years was also imposed on the petitioner. Subsequently, by Ext. P14

(a), Ext. P14 order was modified making the punishment of barring of

increments “with cumulative effect”. The petitioner is challenging

Exts.P8, P14 and P14(a) in this original petition.

4. The contention of the petitioner is that the conclusion of

guilt arrived at by the disciplinary authority and the Government is

totally perverse. He points out that there was no reliable evidence

whatsoever to show that the measurement recorded by the petitioner

was bogus. The petitioner points out that by Ext. P1(a), the B.D.O had

reported to the Collector that there was no basis for the allegation

that the man days reported is not correct. Again, by Ext. P3, the

Executive Engineer stated that from the available quantity of cut soil,

the correct quantum of work done cannot be arrived at. Further, the

Chief Technical Examiner measured the pond as 47 m. x 26.40 m.

whereas the Executive Engineer measured it as 62 m. x 28 m. That

itself, according to the petitioner, shows that there was serious

infirmities in the measurements. He would further point out that

although the petitioner had submitted Ext. P5 reply running into 5

pages to Ext. P4 memo of charges in Ext. P6, all what has been

stated is that the defence statement submitted by the petitioner was

examined with reference to the inspection note of the Chief Technical

O.P. No. 12524/2001 -: 4 :-

Examiner and other connected records and found that the petitioner

was responsible for non-payment of Rs. 7165/- made to the contractor

without stating as to how that conclusion was arrived at and without

discussing the elaborate reply given by the petitioner. He further

submits that it was after two years of his filing an appeal that the

Government came up with a show cause notice for enhancing the

punishment. To the same, the petitioner submitted very detailed

reply. However, the petitioner was not afforded an opportunity of

being heard and he was also not informed about the result. He

further points out that Ext. P14 has been modified by Ext. P14(a)

without an opportunity of being heard to the petitioner.

5. A counter affidavit as been filed by the 3rd respondent

refuting the contentions of the petitioner.

6. I have considered the rival contentions in detail.

7. I am inclined to agree with the counsel for the petitioner.

Apart from the fact that the amount involved is very low, I find that

the measurement recorded was not consistent. The Chief Technical

Examiner is stated to have returned a measurement of 47 m. x 26.4

m. whereas the Executive Engineer had returned a measurement of

62 m. x 28 m. in Ext. P3. The difference is very substantial, perhaps

sufficient cover the difference now sought to be recovered.

Therefore, while passing orders of punishment on the petitioner, that

too, without an enquiry, the disciplinary authority had a duty to

explain this discrepancy. Nothing of that sort is stated in the orders

imposing punishment. As such, I find that Ext. P8 order is perverse in

so far as relevant materials have not been considered by the

disciplinary authority and no reasons are mentioned in the orders

finding the petitioner guilty.

8. Apart from that, when the Government wanted to enhance

O.P. No. 12524/2001 -: 5 :-

the punishment to one of barring of increments with cumulative effect

in addition to recovery of loss imposed by the disciplinary authority,

the Government had a duty to afford the petitioner an opportunity of

being heard. There is nothing to indicate that the petitioner has been

heard before passing Exts. P14 and P14(a). In fact, there is nothing to

indicate that Exts. P14 and P14(a) had been served on the petitioner

at all.

For all the above reasons, I am satisfied that the impugned

orders are perverse, violative of principles of natural justice and

unsustainable. Accordingly, the same are quashed.

Sd/- S. Siri Jagan, Judge.

Tds/