High Court Kerala High Court

T.K.Simon vs Oil Palm India Limited on 16 March, 2010

Kerala High Court
T.K.Simon vs Oil Palm India Limited on 16 March, 2010
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

AS.No. 669 of 1999()



1. T.K.SIMON
                      ...  Petitioner

                        Vs

1. OIL PALM INDIA LIMITED
                       ...       Respondent

                For Petitioner  :SRI.RAJEEV V.KURUP

                For Respondent  :SRI.JOSEPH MARKOSE (SR.)

The Hon'ble MR. Justice HARUN-UL-RASHID

 Dated :16/03/2010

 O R D E R
                      HARUN-UL-RASHID,J.
                --------------------------
                      A.S.NO.669 OF 1999
                --------------------------
               DATED THIS THE 16TH DAY OF MARCH, 2010

                            JUDGMENT

Plaintiff in O.S.No.169/95 on the file of the Principal

Sub Court, Kottayam is the appellant. The suit was filed for

realisation of Rs.38,372.34ps. with future interest at 18% per

annum on the principal amount from the defendant. The trial

court dismissed the suit. Hence this appeal. The parties

hereinafter are referred to as the plaintiff and defendant as

arrayed in the suit.

2. The plaintiff’s case is that he was entrusted with

the work of thermal insulation of pipe for the defendant’s factory

in Kollam District. The defendant is the Oil Palm India Ltd.,

a Government of Kerala Enterprises. The plaintiff had quoted

only for thermal insulation using mineral wool as per IS 7413/81.

But the Project Engineer of the defendant company insisted

for finishing with aluminium sheets. The plaintiff agreed

-2-
A.S.No.669/99

to do so only on condition of paying extra payment for using

aluminium sheet. The plaintiff completed the work by using

aluminium sheet and claimed Rs.19,062.34ps. The further case of

the plaintiff is that he offered to do the work on condition that

the tax payable for the materials used by him shall be paid extra.

According to him, he has to spend Rs.12,890/- for purchase of

additional materials.

3. The defendant company contended that since the

parties had performed their respective obligations under the

contract, the contract stood discharged and that the plaintiff is

estopped from claiming any amount. It is also stated in the

written statement that the work was completed by the plaintiff as

per the tender specifications and that the amount quoted for the

work includes protective finishing using aluminium sheet and not

as stated by the plaintiff. According to the defendant, the

protective finishing using aluminium sheet is not an extra work.

One of the finishing materials, which is specified in Ext.A10 is ”

-3-
A.S.No.669/99

Indian Standard Code of Practice for Industrial Application and

Finishing of Thermal insulating materials at temperatures above

40 C and upto 700 C ”. It is also stated that the plaintiff is not
o o

entitled to claim any amount under the heads mentioned in the

plaint, that the Company had acted only according to the terms

of the contract and they prayed for dismissal of the suit.

4. The plaintiff produced Ext.A1 work order dated

29/9/1992. In Ext.A1 the company informed the plaintiff that ‘we

have pleasure in placing an order on you for the installation of

piping, tanks and pumps at Chithara Factory near Anchal in

Kollam District on the following terms and conditions.’ Ext.A1

also contains the nature of work to be carried out and completed.

The amount payable to the plaintiff is stated in schedule I, II and

III attached to the work order Ext.A1. It is further stated that the

price quoted is inclusive of all expenses, that the prices shall be

confirmed and no explanation shall be permitted during the

period of contract. Clause VIII of Ext.A1 stipulates that the

-4-
A.S.No.669/99

contract work shall be of best quality and workmanship

according to the latest engineering practices and that in case of

poor workmanship noticed, such work will have to be repaired/

replaced/modified at the cost and risk of the contractor. Clause 8

of the page under the head “Scope of work” in Ext.A1 stipulates

that the insulation for steam and as applicable for oil lines shall

be arranged by the contractor and the work shall be carried out as

per IS-7413/1981. Reference to IS-7413/81 is Ext.A10

specifications.

5. Ext.A10 is the Indian Standard code of Practice for

Industrial Application and Finishing of Thermal Insulating

materials at temperatures above 400C upto 7000C. Clause 5 deals

with finishing. Clause 5.2 deals with protective finishes. It

narrated that the following are the commonly applied protective

finishes. Clauses 5.2.1 to 5.2.6 deal with different types of

protective finishings. Clause 5.2.3. is the relevant clause, which

deals with ‘sheet metal’ — aluminium, galvanized iron or mild

-5-
A.S.No.669/99

steel sheet of suitable thickness as agreed to between the

purchaser and the applicator.

6. Referring to Ext.A9 responding to the invitation of

tender the plaintiff quoted the rates for doing the work. In the

letter attached to the rates quoted the plaintiff has stated that the

tax on materials used shall be paid extra. The learned counsel

for the plaintiff contended that he is entitled to realise the amount

under the two heads mentioned above. According to him,

finishing of insulation with aluminium is not a work covered by

the tender and the work order and therefore he is entitled to

realise the amount spent for purchase and installation of

aluminium sheet. Since it is an extra work, payment has to be

made. I have quoted the conditions relating to the materials to be

applied for the insulation work by referring to Ext.P10 standard

specifications. I have also quoted the relevant paragraph in

Ext.A10. The materials to be applied includes the aluminium

sheets as well. Therefore, the contention of the plaintiff that the

-6-
A.S.No.669/99

finishing work done by using aluminium sheet is an extra work

and that he is entitled to extra payment cannot stand. The learned

counsel for the appellant contended that the claims towards sales

tax ought to have been allowed by the court below. According to

him, the defendant did not deny the claims made in Ext.A9 letter

at the time of accepting the tender. Therefore, the condition in

Ext.A9 letter that the tax paid by him for purchase of the

materials shall be paid in addition to the rate agreed. Ext.A9 is

the offer letter addressed to the defendant-company. The rate

quoted is attached to Ext.A9. Schedule 1,2,3 and 4 were

accepted. In the covering letter it is stated that the tax if any

applicable shall be paid extra. Placing reliance on Ext.A9 the

learned counsel contended that his offer was accepted by the

company and therefore the company is liable to pay the amount

incurred by the plaintiff towards payment of tax. It is true that

the plaintiff claimed extra amount towards the tax paid. Ext.A9

is dated 20/2/92. Several months later, the company issued the

-7-
A.S.No.669/99

work order for installation of piping, tanks and pumps. Ext.A1 is

the work order dated 29/9/1992, which contains the terms and

conditions, the rate quoted and accepted by the company etc. The

work order also contains several paragraphs dealing with the

scope of work and technical specifications, terms of payment,

completion period, security deposit, quality and workmanship

etc. The accepted rate for the work was mentioned in Ext.A1

work order as Schedule I, II and III. The next page is under the

head “Scope of work”. Item No. 8 of the scope of work

stipulates that the insulation for steam and as applicable for oil

lines shall be arranged by the contractor and the work shall be

carried out as per IS-7413/1981. Ext.A9 does not contain any

condition in addition to the amount payable for the work, which

was in detail stated in Schedule I to III, stipulating payment

to the plaintiff towards the amount paid by him as tax. So

long as the condition does not contain any stipulation for

making additional payments other than what was agreed in

-8-
A.S.No.669/99

Ext.A1 work order, it is difficult to accept the case of the plaintiff

that he is entitled to the amount paid by him towards sales tax for

the purchase of materials used for carrying out the contract

work. Ext.A1 work order contains the terms and conditions for

doing the work and also the rates payable to the plaintiff. Ext.A1

shows that the plaintiff agreed the terms and conditions stipulated

in Ext.A1 order and carried out the work. After finishing the

work, he cannot turn round and say that the defendant company

is liable to pay the amount not agreed to be paid, as per Ext.A1

work order.

7. The trial court examined the questions in the light of

the oral and documentary evidence adduced by the parties. The

trial court referred to various provisions in IS-7413/1981

(Ext.A10). The trial court observed that it is clear that even

before the plaintiff started the work, he was aware of the fact

that the finishing should be done with aluminium sheet. The trial

court further observed that the defendant in Ext.A4 reply has

-9-
A.S.No.669/99

denied the claim of the plaintiff and directed the plaintiff to

complete the work with aluminium sheet. I have already

discussed and concluded that finishing of insulation with

aluminium is not an extra work but the aluminium sheet has to be

used for protective covering and going by the relevant clauses in

Ext.A10 specifications, I agree with the finding of the trial court

that the finishing of insulation with aluminium covering is not an

extra item of work and the plaintiff’s claim on that ground is

unsustainable. I have discussed the plaintiff’s claim for the

amount paid as tax for purchase of the materials and took the

view that the plaintiff is not entitled to claim under the head ‘paid

as tax’. The trial court examined the question and held that

Ext.A9 is insufficient to claim any amount towards the sales tax

paid by the plaintiff. The trial court also accepted the contention

of the defendant-company that there was no agreement between

the parties to pay any amount towards sales tax and therefore the

claim of the plaintiff on this count cannot be allowed. In the

-10-
A.S.No.669/99

aforesaid circumstances, I do not find any reason to interfere with

the findings recorded by the court below. The view taken by the

court below is the correct view in the facts and circumstances of

the case.

In the result, the appeal fails and accordingly

dismissed. No order as to costs.

HARUN-UL-RASHID,
JUDGE.

kcv.

-11-
A.S.No.669/99

HARUN-UL-RASHID,J.

————————–

A.S.NO.669 OF 1999

————————–

JUDGMENT

16TH MARCH, 2010