High Court Kerala High Court

T.V.Jacob vs The Chief Engineer (Hrm) on 9 July, 2008

Kerala High Court
T.V.Jacob vs The Chief Engineer (Hrm) on 9 July, 2008
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C).No. 20641 of 2008(G)


1. T.V.JACOB, S/O.VARKEY,
                      ...  Petitioner

                        Vs



1. THE CHIEF ENGINEER (HRM)
                       ...       Respondent

2. THE KERALA STATE ELECTRICITY BOARD,

                For Petitioner  :SRI.C.ARUN PRASANTH

                For Respondent  : No Appearance

The Hon'ble MR. Justice V.GIRI

 Dated :09/07/2008

 O R D E R
                          V.GIRI, J
                        -------------------
                     W.P.(C).20641/2008
                        --------------------
             Dated this the 9th day of July, 2008

                        JUDGMENT

Petitioner is working as Electrician Grade-III,

currently stationed at Idamalayar. He is scheduled to retire

on 30.11.2009. He is a native of Kothamangalam. Due to

his illness he has sought for a posting in Kothamangalam

Section. Petitioner points out that there are vacancies in

the Camp Section, Account Closing Unit, KSEB, at

Kothamangalam. Exts.P4 and P4(a) are pending before the

first respondent.

2. Having heard learned counsel for the petitioner and

learned Standing Counsel for the Board and taking note of

the fact that the petitioner is due to retire on 30.11.2009,

writ petition is disposed of directing the first respondent to

consider the petitioner’s request as contained in Exts.P4

and P4(a), and do the needful within four weeks from the

date of receipt of a copy of this judgment. Petitioner shall

produce a copy of the writ petition along with the copy of

the judgment before the first respondent.

V.GIRI,
Judge
mrcs