High Court Kerala High Court

The General Manager vs M/S.Delta Granites And Sand on 7 July, 2008

Kerala High Court
The General Manager vs M/S.Delta Granites And Sand on 7 July, 2008
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WA.No. 1197 of 2008()


1. THE GENERAL MANAGER,
                      ...  Petitioner
2. THE DIVISIONAL RAILWAY MANAGER

                        Vs



1. M/S.DELTA GRANITES AND SAND,
                       ...       Respondent

                For Petitioner  :SMT.A.RAJESWARI, SC, RAILWAYS

                For Respondent  : No Appearance

The Hon'ble MR. Justice J.B.KOSHY
The Hon'ble MR. Justice P.N.RAVINDRAN

 Dated :07/07/2008

 O R D E R
                      J.B.Koshy & P.N.Ravindran, JJ.
                       =====================
                          W.A.No.1197 of 2008
                       =====================

                  Dated this the 7th day of July, 2008.

                               JUDGMENT

Koshy,J.

In pursuance to Ext.P7 tender notice issued by the second

respondent inviting tenders for the work of collection and supply of

ballast in Chengannur depot (including loading and unloading), the writ

petitioner submitted his tender. As per the eligibility condition, the

tenderer has to complete at least one similar single work for a minimum

value of 50% of the advertised tender value of work. After completion of

the process of pre-qualification and selection, the offer made by the

petitioner was accepted by the second respondent (appellant) and the

same was conveyed to the petitioner by Ext.P1. The relevant portion of

acceptance is as follows:

“The letter of acceptance issued is a binding contract

between the Railway and the contractor and the date of

completion will be reckoned from the date of issue of this

letter only and therefore you may please make

arrangements to commence the work immediately.”

2. The petitioner submitted performance guarantee for

Rs.4,55,850/-. The solvency certificate was also produced as can be seen

in Exts.P3 and P5. Acting upon Ext.P1, the petitioner has manufactured

WA 1197/08 -: 2 :-

the track ballast of more than 60% of the volume required for the work

and he has acted on the work order issued. Samples were supplied.

Ext.P4 report shows that the samples were best and found suitable.

Thereafter, the second respondent issued Ext.P6 notice stating that it

was advised that the above work had been cancelled due to

administrative reasons. We don’t know what is the administrative

reasons. The reason is not known to him. Before this Court, the reasons

stated were not administrative reasons. It is not stated in Ext.P6 that

cancellation was due to any mistake or the petitioner was ineligible. It is

stated before this Court that the petitioner was only a supplier and not a

direct contractor to P.W.D. or K.S.E.B. and that is the reason for

cancelling the contract.

3. Ext.P7 is the tender notice. The pre-qualification norms required

to be satisfied by the tenderer is the execution of at least one similar

single work for a minimum value of 50% of advertised tender value of

work in the last three financial years. The work notified is only collection

and supply of ballast as the description of the work given in Ext.P1.

Apart from the collection and supply of approved quality of machine

crushed track ballast, the work also involves loading ballast into railway

wagons and coffers by using contractors, labour, etc. and unloading the

same as directed by the engineer in-charge of the work. The nature of

work only says collection and supply of tract ballast in Chengannur depot

and hence what is required to be satisfied by the contractor is

WA 1197/08 -: 3 :-

completion of at least one work similar to what is notified for the value

specified and within the period prescribed. Exts.R2(a) to R(2)(i)

certificates produced by the petitioner show that the petitioner is fully

eligible.

4. The learned single Judge considered the matter and held as

follows:

“In my view, the requirements of Ext.P7 or Ext.P1 are

fully satisfied by the certificates produced and the

inadequacies pointed out are not specified in the tender

notice. Exts.R2(a) to R2(i) indicate that the petitioner has

supplied similar materials to the contractors concerned.

Therefore, these certificates satisfy the requirements of

Ext.P7 and it is not the requirement of Ext.P7 that the

petitioner should be a direct contractor to P.W.D., Kerala

State or K.S.E.B. Thus, the certificates, which were

furnished by the petitioner are in full compliance with

Exts.P7 and P1. Therefore the theory of mistake now

canvassed in the counter affidavit is a totally unfounded

one. Necessarily, therefore Ext.P6 issued to the petitioner

also cannot be sustained.”

The writ petitioner has already acted on the basis of acceptance of the

tender. The public authority has a duty to act fairly and reasonably. Even

though there are inherent limitations in exercising judicial review in

contractual matters, power of judicial review can be extended to prevent

arbitrariness of if there is also procedural irregularity, wednesbury

arbitrariness or manifest error or lack of bonafides. The learned single

WA 1197/08 -: 4 :-

Judge set aside Ext.P6 as it was arbitrary and lacking in bonafides

resulting in manifest error. We fully endorse the view of the learned

single Judge. There is no ground to interfere with the impugned

judgment.

The Writ Appeal is dismissed.

J.B.Koshy,
Judge.

P.N.Ravindran,
Judge.

ess 19/7