High Court Punjab-Haryana High Court

The State Of Haryana And Others vs Wazir Singh (Contractor) on 20 August, 2009

Punjab-Haryana High Court
The State Of Haryana And Others vs Wazir Singh (Contractor) on 20 August, 2009
RSA No. 3074 of 2009                                       (1)

        IN THE HIGH COURT OF PUNJAB AND HARYANA AT
                        CHANDIGARH

                                       RSA No. 3074 of 2009
                                       Date of Decision: 20.8.2009


The State of Haryana and others                            ......Appellants

             Versus

Wazir Singh (Contractor)                                   .......Respondent

CORAM: HON’BLE MR. JUSTICE HEMANT GUPTA.

1. Whether Reporters of local papers may be allowed to see the judgment?

2. To be referred to the Reporters or not?

3. Whether the judgment should be reported in the Digest?

Present: Shri Kulvir Narwal, Additional AG, Haryana,
for the appellants.

HEMANT GUPTA, J. (Oral).

The defendants are in second appeal aggrieved against the

judgment and decree passed by the Courts below, whereby suit for

declaration challenging the forfeiture of performance security of

Rs.1,17,200/-, was decreed.

The plaintiff-respondent was granted contract for construction

of change of alignment of Jind Distributory No. 7 for RD 4000 to 8360 and

relinking at RD 23500 on existing alignment. It is the case of the defendants

in the written statement that even if it was not possible for the department to

make the entire site available to the contractor, the contractor should have

arranged his working programme in terms of Clause 11 of the Conditions of

Contract. Therefore, the plaintiff is not entitled to the declaration sought for.

RSA No. 3074 of 2009 (2)

Both the Courts have found that not only the site was not made

available, but even the drawings of `L’ Section were not finalised and were

in fact, changed thrice. Therefore, the defendants are not entitled to

forfeiture of the performance security.

Learned counsel for the appellants has vehemently argued that

even in the absence of handing over of the complete site, the plaintiff could

have started the construction work and having failed to do so, the plaintiff is

not entitled to the declaration sought for.

It is not the case of the defendants that some site was made

available on which the plaintiff could possibly start the work. In fact, not

only the site was not made available, but even the drawings of the work

were not finalized. In view of the said situation, forfeiture of the

performance security is wholly unjustified and not sustainable in the eyes of

law, as has been rightly found by the Courts below.

Consequently, I do not find any patent illegality or material

irregularity in the finding recorded or that the finding recorded gives rise to

any substantial question of law in the present second appeal.

Hence, the present appeal is dismissed.

(HEMANT GUPTA)
JUDGE

20.8.2009
ds