High Court Punjab-Haryana High Court

Tushar Kumar vs State Of Haryana And Another on 21 August, 2009

Punjab-Haryana High Court
Tushar Kumar vs State Of Haryana And Another on 21 August, 2009
CRM-M No.32091 of 2008 (O&M)                -1-


IN THE PUNJAB AND HARYANA HIGH COURT AT CHANDIGARH


                                     CRM-M No.32091 of 2008 (O&M)

                                     Date of Decision: 21.8.2009


Tushar Kumar
                                                  ..Petitioner.

Vs.

State of Haryana and another
                                                  ..Respondents.


CORAM: HON'BLE MR.JUSTICE RAKESH KUMAR JAIN


Present :   Mr.R.S.Cheema, Sr.Advocate with
            Ms.Tanu Bedi, Advocate for the petitioner.

            Mr.Narender Sura, AAG Haryana for the State/respondent.

            Mr.Harbhagwan Singh, Sr.Advocate with
            Mr.Amit K.Singh, Advocate for respondent No.2.


RAKESH KUMAR JAIN, J.

This is a petition under Section 438 Cr.P.C. for grant of

anticipatory bail in case registered vide FIR No.141 dated 6.10.2008 under

Sections 406/420/506/120-B IPC at Police Station DLF Phase-I, Gurgaon.

The aforesaid FIR has been registered on the complaint of

H.S.Lamba, Managing Director of M/s Sneh Developers Pvt. Ltd. Briefly,

the allegations contained in the FIR are that the petitioner, who is managing

Director of GTM Builders and Promoters Pvt. Ltd., approached the

complainant for the construction of multi-storeyed building on an area of

about 1 acre purchased by him at village Gowal Pahari, Gurgaon. The

building was to be known as Tower No.11. The petitioner had assured the
CRM-M No.32091 of 2008 (O&M) -2-

complainant company that his company is a cash rich company and will pay

the running bills of the construction well within time. On this assurance, the

complainant company entered into an agreement with the petitioner on

10.3.2005 and started construction of the building. It was agreed upon

between the parties that the petitioner shall supply cement and steel which

shall be adjusted in the cost of the bills. After a few months of the inception

of the construction, the petitioner delayed the payment of running bills on

the ground that funds received in the proposed building have been blocked

in another land purchased by him. He requested the complainant to carry on

the construction work and on his request and assurance, funds were

arranged from the market on a high rate of interest and invested the same in

purchasing the machinaries and building construction material. Since there

was a dispute between the parties with regard to construction and delayed

payment of money, an addendum agreement was executed on 28.9.2006 as

per which the company owned by the petitioner, assured the complainant

that they would make the payment within 10 days on the submission of the

bills. But despite that the bills were not paid in time, however, a fresh

memorandum of understanding was executed on 25.3.2008 as per which the

petitioner had agreed to pay Rs.1.25 Crores for the escalation charges in the

construction material for structure raised as on 25.3.2008 and also agreed to

pay the running bills in time with penalty for delay and the entire building

work was scheduled to be completed by December 2008. It is also alleged

that as soon as the complainant Company completed the structure of 96 flats

of 17 floor of the multi-storeyed tower and were completing the finishing

work of the flats at great speed, the petitioner showed his true colours and

stopped making payment of running bills. Last bill dated 17.7.2008 of
CRM-M No.32091 of 2008 (O&M) -3-

Rs.42.62 lacs was not paid but only Rs.5 lacs was paid for making payment

of wages to the labour. The total outstanding as on 31.8.2008 against GTM

Company is 2.88 Crores. It is also alleged that the petitioner had threatened

the complainant and had also bribed his employees.

Before coming to this Court, the petitioner had applied for

anticipatory bail before the Court below which was dismissed by the

Additional Sessions Judge, Fast Track Court, Gurgaon on 11.10.2008.

Learned counsel for the petitioner has vehemently argued that

the dispute between the parties is essentially of a civil nature which is borne

out from the documents itself, therefore, custodial interrogation is not

required. It is submitted that on 10.3.2005 agreement (Annexure P-2) was

entered into between the parties as per which the petitioner had given the

job of construction to the complainant on turn-key basis. The date of

commencement of work agreed between the parties was 10.3.2005 and the

date of completion was 31.10.2006. Since the work of contract should have

been completed before the stipulated date and was not completed, therefore,

vide (Annexure P-3) registered notice was given on 31.7.2006 calling upon

the complainant to remedy the breach within a period of 15 days failing

which the agreement Annexure P-2 shall stand terminated and the balance

work shall be completed through other agency at the risk and cost of the

complainant. Thereafter, addendum to the agreement dated 10.3.2005

(Annexure P-2) was executed on 28.9.2006 (Annexure P-4) in which it was

agreed by the complainant that they would furnish bank guarantee in favour

of the petitioner for a sum of Rs.50 lacs at the time of signing its

performance of the contract and shall issue five cheques of Rs.10 lacs each

without mentioning the date, in favour of the petitioner. It was also provided
CRM-M No.32091 of 2008 (O&M) -4-

in the addendum that the petitioner shall have right of lien on all

machinaries and equipments deployed or to be deployed at site under the

completion of GTM Residency Tower in all respects. If the complainant

commits any default in performance of the contract then the petitioner shall

have the right of lawful possession of the said machinery and equipment

and shall also have a right to dispose them off for the purpose of realisation

of damages. It is further submitted that despite the addendum, the

complainant could not fulfill the commitment, therefore, vide letter dated

5.3.2008 (Annexure P-5) the petitioner exercised his right of lien on all the

machinaries and equipments available at the site to take possession and also

declared that agreement dated 10.3.2005 (Annexure P-2) and addendum

dated 28.9.2006 (Annexure P-4) stand cancelled. It is further submitted that

on 10.3.2008, the petitioner had to issue legal notice (Annexure P-6) to the

complainant on the ground that all the five cheques of Rs.10 lacs were

dishonoured on the ground of `Insufficiency of funds’ but due to some

amicable settlement between the parties, the said legal notice (Annexure P-

6) was withdrawn on 10.3.2008 vide letter (Annexure P-7) and thereafter on

25.3.2008 memorandum of understanding (Annexure P-8) was also

executed between the parties according to which construction work was to

be finished by the complainant by 31.3.2008 positively. Since the work was

not completed, therefore, the petitioner sent a letter of termination of

contract on 29.8.2008 (Annexure P-10) and on 29.8.2008 he also made a

complaint to the Commissioner of Police, Gurgaon against the complainant

that they are threatening the employees of the petitioner. On 20.9.2008, the

petitioner also informed the complainant that since there is clause No.16

with regard to resolving the dispute through Arbitrator, therefore, they were
CRM-M No.32091 of 2008 (O&M) -5-

requested to appoint a sole arbitrator. In the present case, the complainant

filed a reply to the bail application to which the petitioner had also filed a

rejoinder. Besides that the complainant filed an application under Section

340 Cr.P.C.

In response to the arguments raised by the counsel for the

petitioner, counsel for the complainant has vehemently argued that offence

under Section 420 IPC is apparent on the face of it as from the beginning

the complainant was allured by the petitioner for the construction of flats by

assuring him that it is a cash rich company and all the payments shall be

made in time. It is further submitted that Section 406 IPC is also made out

on the basis of the allegations made in the FIR. Since the complainant has

threatened by the petitioner, therefore, Section 506 IPC is also made out. It

is further submitted by the counsel for the complainant that an amount of

Rs.2.92 Crores is still due towards the petitioner, which has not been paid so

far. Learned counsel for the complainant has further argued that in view of

the decision of the Apex Court in the case of Adri Dharan Das Vs. State

of West Bengal (2005) 4 SCC 303, the petitioner is not entitled to

anticipatory bail.

In response to this argument, counsel for the petitioner has

relied upon decision of the Apex Court in Gurbaksh Singh Sibbia etc. Vs.

The State of Punjab AIR 1980 SC 1632 and Savitri Agarwal & Othres

Vs. State of Maharashtra and another 2009(4) Recent Apex Judgments

516. Counsel for the petitioner has further submitted that in terms of the

order passed by this Court dated 11.12.2008, the petitioner has already

joined the investigation. This fact is not disputed by the counsel for the

State.

CRM-M No.32091 of 2008 (O&M) -6-

I have given my thoughtful consideration to the respective

contentions raised by the counsel for the parties and have perused the record

with their assistance.

The resume of the facts originated from the documents on

record shows that it is a business dispute between the parties in which

agreement, addendum to agreement and even memorandum of

understanding have been executed for the purpose of execution of

construction work, which has been delayed for one reason or the other. It is

also brought to the notice of the Court that after a request made by the

petitioner to the complainant for the appointment of arbitrator (Annexure P-

12), a petition has already been filed before the Hon’ble Delhi High Court

for the purpose of appointment of an Arbitrator on 29.5.2009 in which

notice of motion has been issued for 11.9.2009. This Court has found that it

is a dispute with regard to accounting and interpretation of the relevant

provisions of the agreement between the parties because the petitioner is

claiming lien of the plot and machinery on the basis of Clause 3 of the

addendum to the agreement dated 10.3.2005 (Annexure P-2) and the

complainant is claiming escalation in the cost price on the basis of

memorandum of understanding (Annexure P-8) dated 25.3.2008. It is

worthwhile to mention that both addendum (Annexure P-4) and

memorandum of understanding (Annexure P-8) are the part of the main

agreement (Annexure P-2). Since the entire dispute is based upon

documents which according to the petitioner, have already been submitted

to the Investigating Officer and that the petitioner has joined the

investigation, therefore, order dated 11.12.2008 is made absolute. It is

however, directed that petitioner shall join the investigation as and when
CRM-M No.32091 of 2008 (O&M) -7-

called for. He shall also abide by the provisions of Section 438(2) Cr.P.C.

The petition is disposed of.




                                           (Rakesh Kumar Jain)
21.8.2009                                        Judge
Meenu