Bombay High Court High Court

Union Of India And Anr vs Sagar Construction Company And … on 20 November, 2009

Bombay High Court
Union Of India And Anr vs Sagar Construction Company And … on 20 November, 2009
Bench: Anoop V.Mohta
    ndm
                                                   1                                         arbp.545.09.sxw




                                                                                              
                IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                    ORDINARY ORIGINAL CIVIL JURISDICTION




                                                                      
                       ARBITRATION PETITION NO. 545 OF 2009




                                                                     
    Union of India and anr.                                             ... PETITIONERS
         Vs.
    Sagar Construction Company and anr.                                 ... RESPONDENTS




                                                      
                                   --------------
                                 
    Mr. K.R. Chaudhari with N.D. Sharma for the Petitioner.
    Ms. Shilpa Kapil for the Respondents.
                                
                                   --------------

                                             CORAM  :  ANOOP V. MOHTA, J.

th
DATE : 20 November, 2009.

    



    ORAL JUDGMENT

    1               Heard finally.





    2               The   petitioners   have   invoked   Section   34   of   the   Arbitration 

and Conciliation Act, 1996 (for short, the Arbitration Act) thereby,

challenged the award whereby, the learned Arbitral Tribunal has granted

partially three claims i.e. claim Nos. 1, 2 and 8 out of 10 claims and

thereby rejected all other claims.




    3               So far as, the submissions with regard to no claim certificate 




                                                                      ::: Downloaded on - 09/06/2013 15:19:38 :::
     ndm
                                              2                                     arbp.545.09.sxw




                                                                                     

based upon clause 65 of the contract condition, the learned Arbitrator

after going through the material, as well as, the documents on record,

has dealt with in detail and rejected the case of the Petitioners for want of

substantial material to support their case. The reasoning so given just

cannot be said to be perverse and especially as it is based upon

condition of the Contract and the facts and specially when it is based

upon the judgment of the Apex Court reported in 2008(3) Arbitration LR

633 (SC) National Insurance Co. V/s Boghara Polyfab Pvt. Ltd.,

whereby it has been held that the the claim can be raised even after

signing the “No claim certificate” and/or “No further claim”. The claim so

raised after signing of the final bills is distinguished as per the conditions

in question and hence, is arbitrable as per the principle of equity and fair

justice. The submission that, no such claim was raised / agitated, on or

before the Officer, in the present facts and circumstances, is

unacceptable.

4 With regard to claim Nos. 1, 2 and 8, the submission is that

the figures, so refers, have no details about the calculations. The party,

when moved a claim petition before the Arbitrator, has material to support

the claim with figures. The Arbitrator finds that the party has a case

based upon the material and calculations available on record and

accordingly, accepted the same partially, and awarded the amount.





                                                             ::: Downloaded on - 09/06/2013 15:19:38 :::
     ndm
                                                  3                                       arbp.545.09.sxw




                                                                                           
    There   is   no   case   of   want   of   supporting   document   of   bills.     Even 

otherwise, it is difficult to accept that the claim of the Petitioners is

contrary to law and the record for want of contra material on record,

specially when the submission is only with regard to details of amount so

awarded. The Court need to see the award in totality. Some lacuna or

lack of details that itself, in the present case, can not be reason to

interfere with the award. It can not be treated as unreasoned award.

5 With regard to interest, the Arbitrator has awarded the

st
interest from 01 August, 2001 @ 11% per annum. The learned counsel

appearing for the Petitioners conceded to the date of completion of the

work. The final bill needs to be submitted within three months and for

passing after due verification requires six months more. Therefore, I am
st
inclined to restrict the interest, on the amount so awarded, from 01 May,
st
2002 instead of 01 August, 2001. Considering the fact that it is a work

contract / construction contract, the rate of interest restricted @ 9% per
st
annum instead of @11% per annum from 01 May, 2002.

6 The learned counsel appearing for the Petitioners has relied
th
on the order dated 04 September, 2006, passed in Arbitration Petition

No. 200 of 2006 between the same parties. It was admittedly, of some

different contract. The Court cannot overlook the factual reasoning given

::: Downloaded on – 09/06/2013 15:19:38 :::
ndm
4 arbp.545.09.sxw

by the learned Arbitrator considering the material and documents on

record. Therefore, also this order is of no assistance to the Petitioners.

7 Resultantly, the petition is partly allowed and the impugned

award is modified to the above extent, as recorded. The rest of the award

is maintained. There was no other challenge raised.

8

The Petition is accordingly partly allowed, with no order as to

costs.

9 Learned counsel appearing for the Petitioners is seeking stay

of this order. It is rejected.

[ ANOOP V. MOHTA, J ]

::: Downloaded on – 09/06/2013 15:19:38 :::