High Court Punjab-Haryana High Court

Yashpal Dahiya vs State Of Haryana And Another on 1 January, 2009

Punjab-Haryana High Court
Yashpal Dahiya vs State Of Haryana And Another on 1 January, 2009
  IN THE HIGH COURT OF PUNJAB AND HARYANA
                AT CHANDIGARH



                                       F.A.O. No. 1640 of 2008
                                      Date of Decision : December 11, 2008



Yashpal Dahiya, Contractor
                                                             .....Appellant
                                 Versus

State of Haryana and another

                                                          .....Respondents


CORAM : HON'BLE MR JUSTICE T.P.S. MANN


Present :   Mr. Rajender Singh Malik, Advocate


T.P.S. MANN, J.

On 30.3.1996, construction work was allotted to the appellant-

Contractor who was required to start the work on 2.4.1996 and complete it

within a period of six months, i.e. upto 1.10.1996. The time limit was

extended upto 25.9.1997 but the work could not be completed. No further

extension was allowed. This led to a dispute between the Contractor and

the respondent-Department which was referred to the Arbitrator in terms of

Clause 25(a) of the contract. The Arbitrator gave his award dated 2.4.2002

as per which the Contractor was required to pay Rs. 3,26,185/- to the

Department on account of Clause 3(c) of the contract. The Contractor filed

an objection petition under Section 34 of the Arbitration and Conciliation
F.A.O. No. 1640 of 2008 -2-

Act, 1996 (hereinafter referred to as ‘the Act’) for setting aside the award

but the same was dismissed by District Judge, Sonipat on 11.2.2008.

Hence, the present appeal under Section 37 of the Act.

Clause 2 of the contract required the Contractor to strictly

observe the time allowed for carrying out the work as entered in the tender.

This clause reads as under :-

“Clause 2. The time allowed for carrying out of work as

entered in the tender shall be strictly observed by the

Contractor, and shall be reckoned from the date on which

the order to commence work is given to the Contractor.

The work shall throughout the stipulated period of the

contract be proceeded with all due diligence (time being

deemed to be the essence of the contract on the part of the

Contractor) and the Contractor shall pay as compensation

on amount equal to one per cent which the Executive

Engineer may levy on the amount of the estimated cost of

the whole work as shown by the tender for every day that

the work remains un-commenced, or unfinished, after the

proper dates. And further to ensure good progress during

the execution of work the Contractor shall be bound, in all

cases in which the time allowed for any work exceeds one

month to complete one-fourth of the whole of the work

before one-fourth of the whole time allowed under the

contract has elapsed, one-half of the work before one-half
F.A.O. No. 1640 of 2008 -3-

of such time has elapsed and three-fourth of the work

before three-fourth of such time has elapsed. In the event

of the Contractor failing to comply with this condition, he

shall be liable to pay as compensation an amount equal to

one per cent which the Executive Engineer may levy on

the said estimated cost of the whole work for everyday that

due quantity of work remains incomplete provided always

that the amount of compensation to be paid under the

provisions of this clause shall not exceed ten per cent of

the estimated cost of the work as shown in the tender. The

Superintending Engineer on representation in writing from

the Contractor, may reduce the amount of compensation

and his decision in writing shall be final.

The various situations arising out of the Contractor rendering

himself liable to pay compensation were to be resolved in three different

ways which were described in Clause 3 of the agreement as follows :-

“Clause 3: In any case in which under any clause or

clauses of this contract, the Contractor shall have rendered

himself liable to pay compensation amounting to the whole

of his security deposit (whether paid in one sum or

deducted by installments) the Executive Engineer on

behalf of the Government shall have power to adopt any of

the following courses, as he may deem best suited to the

interests of Government.

F.A.O. No. 1640 of 2008 -4-

(a) To rescind the contract (of which rescission notice

in written to the Contractor under the hand of the

Executive Engineer shall be conclusive evidence)

and in which case the security of the Contractor

shall stand forfeited and be absolutely at the disposal

of Government.

(b) To employ labour paid by the Public Works Deptt.

and to supply materials to carry out the work, or any

part of the work debiting the Contractor with the

cost of the labour and the price of the materials (of

the amount of which cost and price a certificate of

the Executive Engineer shall be final and conclusive

against the Contractor) and crediting him with the

value of the work done, in all respects in the same

manner and at the same rates as if it had been carried

out by the Contractor under the terms of his

contract; the certificate of the Executive Engineer as

to the value of the work done shall be final.

(c) To measure up the work of the Contractor, and to

take such part thereof as shall be unexecuted out or

his hands, and to give it to another Contractor to

complete. in which case any expenses which may be

incurred in excess of the sum which would have

been paid to the original Contractor if the whole
F.A.O. No. 1640 of 2008 -5-

work had been executed by him (of amount of which

excess the certificate in writing the Executive

Engineer shall be final and conclusive) shall be

borne and paid by the original Contractor and may

be deducted from any money due to him by

Government under the Contractor or otherwise, or

from his security deposit or the proceeds of sale

thereof or a sufficient part thereof.”

On account of the Contractor not completing the work even

within the extended period, i.e. upto 25.9.1997, the contract was rescinded

vide order dated 25.8.1998 in terms of Clause 3 and ultimately, the work

was re-allotted to another Contractor on risk and cost basis. Accordingly,

on the basis of the available evidence, the Arbitrator concluded that an

amount of Rs. 3,26,185/- as on 28.3.2002 was due which was to be paid by

the Contractor to the Department.

It is submitted on behalf of the Contractor that the work was

started in right earnest and the excavation of s/s tank completed before the

monsoons set in but cement and steel were supplied in sufficient quantity

only in May and June, therefore, the excavated portion could not be secured

and was filled up with the rain-water.

The Department had produced in its evidence the bin cards of

cement and steel which showed that they were available in good quantity

during 5/96 onwards but it was the Contractor who did not come forward to
F.A.O. No. 1640 of 2008 -6-

complete the work after 7/96 and even when extension of time was granted

upto 25.9.1997.

In view of the above, no interference is called for in the

impugned order passed by District Judge, Sonipat whereby objection

petition filed by the Contractor against the award dated 2.4.2002 was

dismissed.

The appeal has no merit and, resultantly, dismissed.





                                                    ( T.P.S. MANN )
December 11, 2008                                        JUDGE
satish