High Court Rajasthan High Court - Jodhpur

Chiman Lal vs Rajasthan Avasan Mandal & Ors on 19 December, 2008

Rajasthan High Court – Jodhpur
Chiman Lal vs Rajasthan Avasan Mandal & Ors on 19 December, 2008
                      S.B.Civil Misc. Application No.16/2008 (Arbitration Application)
                                                                 Chiman Lal Middha
                                                                                    vs
                                                      Rajasthan Housing Board & ors.
                                     1

 IN THE HIGH COURT OF JUDICATUARE FOR RAJASTHAN AT
                      JODHPUR.

                                 ORDER

       Chiman Lal Middha            vs.     Rajasthan Housing Board
                                            & ors.

            S.B.    Civil  Misc.    Application   No.16/2008
            ( Arbitration Application ) under Section 10 & 11
            of the Arbitration and Conciliation Act, 1996 for
            appointment of an Arbitrator.

   Date of Order:                        December 19th, 2008.

                           PRESENT
               HON'BLE MR. PRAKASH TATIA, J.

Ms. Rekha Borana for the applicant.

BY THE COURT:

Application under Sections 10 and 11 of the Arbitration and

Conciliation Act, 1996 (for short ‘the Act of 1996’) was submitted

before the court of District & Sessions Judge, Hanumangarh by

applicant Chiman Lal Middha, Proprietor of M/s Chiman Lal Rakesh

Kumar, 158 Durga Colony, Hanumangarh wherein notices were

issued to the non-applicants who submitted reply before the court

below. In view of the Notification No.2/SRO/2006 dated 31.5.2006,

the court of District Judge lost its jurisdiction and, therefore, the

arbitration application has been transferred to this Court by the

order of the learned Addl. District & Sessions Judge No.1,

Hanumangarh to whom the matter was transferred by the learned
S.B.Civil Misc. Application No.16/2008 (Arbitration Application)
Chiman Lal Middha
vs
Rajasthan Housing Board & ors.

2

District Judge. The order dated 27.2.2008 for sending the matter

to the High Court was passed by the court after hearing both the

parties. Upon receipt of the matter, this petition has been

registered in the High Court and the notices were issued to the

respondents. Inspite of service of notices, the respondents did not

appear, therefore, only counsel for the applicant was heard.

As per the facts mentioned in the application, a notice

inviting tender No.7/98-99 was issued by the Rajasthan Housing

Board for construction of certain quarters. In the said process of

award of the contract, the applicant states that he took part in the

negotiation wherein he gave rates for the work in question and

according to the petitioner, he was entitled to the work order but

accepted the rates given by non-applicant no.2 with different

rates. According to the applicant, if the rates given by the

applicant would have been accepted then the total consideration

for the contract would have been Rs.17,16,611/-, whereas that has

been reduced in the work order No.2697 dated 11.2.1999 to

Rs.16,19,587/-. When the applicant received the work order

No.2697 dated 11.2.1999, the applicant immediately protested

against it by letter dated 16.2.1999 but the correct work order was

not issued containing the correct amount of the work. The

applicant after giving more facts about how the work was done and

what is the claim of the applicant, submitted that he is entitled to
S.B.Civil Misc. Application No.16/2008 (Arbitration Application)
Chiman Lal Middha
vs
Rajasthan Housing Board & ors.

3

issuance of fresh contract containing the correct rates of the

contract and alternative, if it is found that the work order time has

expired on 16.12.1999, then it may be held that the Rajasthan

Housing Board is responsible for non-completion of the work and

the respondents may be directed to prepare the final bill and pay

Rs. 2,29,163/- to the applicant. In addition to above, the applicant

has raised other claims and gave notice to the respondents under

Clause 23 of the contract containing the arbitration clause for

appointment of the arbitrator and also sent a DD of Rs.250/- to the

respondent for that purpose. According to the applicant, even

after the notice, the arbitrator has not been appointed by the

respondents and, therefore, the applicant is seeking appointment

of arbitrator through the court under Sections 10 and 11 of the Act

of 1996.

The respondents submitted reply before the court below and

admitted that work order of Rs. 16,19, 587/- was given to the

applicant and this is the correct cost of the work. The applicant

was supposed to deposit the performance guarantee of Rs.81,000/-

which was admitted by the applicant. Thereafter, the applicant

started work from 17.2.1999 which should have been completed

before or on 16.12.1999 but the applicant did not complete the

work. The applicant’s other claims were also denied and it is stated

that Clause 23 of the contract could have been invoked only when
S.B.Civil Misc. Application No.16/2008 (Arbitration Application)
Chiman Lal Middha
vs
Rajasthan Housing Board & ors.

4

the work is completed by the contractor. The respondents

submitted that the arbitrator cannot be appointed in the facts of

the case.

Since the contract is admitted and there is clause of

arbitration and which has been raised by the party to the

arbitration agreement and the respondents inspite of notice, have

not appointed arbitrator, therefore, it will be appropriate to

appoint an arbitrator.

Shri Jagjit Singh, Retired Addl. Chief Engineer, Irrigation,

12-A, Sadul Ganj, Near State Garage, Bikaner is appointed as

arbitrator. The fees for the arbitrator will be Rs.15,000/- and the

arbitrator shall be paid Rs.5000/- as initial fees and the office

expenses for the arbitral proceedings shall be payable by the

applicant initially and the arbitrator while deciding the dispute

may fix the liability and responsibility for payment of the fees

which shall be payable as per the order of the arbitrator.

The application is, therefore, allowed accordingly.

A copy of this order be sent forthwith to the arbitrator.

(PAKASH TATIA),J.

mlt