Allahabad High Court
Pradeep Kumar Sharma vs Deputy Director Of … on 27 July, 2010
Court No. - 5 Case :- WRIT - B No. - 43305 of 2010 Petitioner :- Pradeep Kumar Sharma Respondent :- Deputy Director Of Consolidation, Azamgarh And Others Petitioner Counsel :- A.P. Singh Respondent Counsel :- C.S.C. Hon'ble Sabhajeet Yadav,J.
Heard learned counsel for the petitioner.
It is stated that revision under Section 48 of U.P.C.H. Act is pending
before Dy. Director of Consolidation, Azamgarh since 1996. In case, the
proceeding of said revision has not been stayed by any superior court, the
same shall be decided expeditiously, preferably within a period of three
months from the date of production of certified copy of this order before him.
With the aforesaid observation and direction, writ petition stands
disposed of finally.
Order Date :- 27.7.2010
LJ/-