IN THE HIGH COURT OF KERALA AT ERNAKULAM
WP(C) No. 2224 of 2007(M)
1. SHIRILSON MATHEW, MANAGING PARTNER,
... Petitioner
Vs
1. THE STATE OF KERALA, REPRESENTED BY
... Respondent
2. THE PRINCIPAL SECRETARY,
3. THE DIRECTOR OF PUBLIC INSTRUCTIONS,
4. THE CHIEF ENGINEER,
5. THE SUPERINTENDING ENGINEER,
6. THE EXECUTIVE ENGINEER,
For Petitioner :SRI.AJITH KRISHNAN
For Respondent :GOVERNMENT PLEADER
The Hon'ble MR. Justice THOTTATHIL B.RADHAKRISHNAN
Dated :01/03/2007
O R D E R
THOTTATHIL B.RADHAKRISHNAN, J
-------------------------------------------
W.P(C).No.2224 OF 2007
-------------------------------------------
Dated this the 1st day of March, 2007
JUDGMENT
The claim of the petition is for release of amounts due to
him for the contract works done. The counter affidavit of the 4th
respondent shows that in view of the letter of credit already
available, there were certain recommendations and that, as of
now, further letters of credit for the work of construction of
G.V.Raja Sports School will be considered by the Government on
production of copies of technical sanction and accounts of part
payments. The Government letter is stated to be gaining the
attention of the competent officer. Hence this writ petition is
disposed of directing that the details called for by the 4th
respondent shall be made available by the second respondent at
the earliest and the reply to the Government letter dated
17.1.2007 shall also be issued without delay. The amounts due
to the petitioner will then be quantified and released, at the
earliest.
THOTTATHIL B.RADHAKRISHNAN
Judge
kkb.