High Court Punjab-Haryana High Court

Vinod Kumar Ghai vs State Of Punjab & Ors on 15 December, 2008

Punjab-Haryana High Court
Vinod Kumar Ghai vs State Of Punjab & Ors on 15 December, 2008
CWP No. 6015 of 2005.                                ::-1-::

IN THE HIGH COURT FOR THE STATES OF PUNJAB AND
               HARYANA AT CHANDIGARH.

                          C.W.P. No. 6015 of 2005.
                          Date of Decision: 15th December, 2008.
Vinod Kumar Ghai                 ..Petitioner through
                                 Mr. Arun Jain, Sr. Advocate with
                                 Mr. Amit Jain, Advocate.
            Versus

State of Punjab & Ors.           Respondents through

Mr. H.S.Mattewal, AG, Punjab with
Mr. Parveen Goel, Addl.AG, Punjab.

Mr. APS Mann, Advocate.

CORAM:

HON’BLE MR. JUSTICE SURYA KANT.

1. Whether Reporters of local papers may be allowed to see the judgment?

2. To be referred to the Reporters or not?

3. Whether the judgment should be reported in the Digest?

SURYA KANT, J. [ORAL)

This Civil Writ Petition seeks quashing of the notifications

dated 25.2.2004 and 16.2.2005 [Annexures P1 and P9] issued under

Sections 4 and 6 of the Land Acquisition Act, 1894 [for short ‘the Act’]

whereby land measuring 26 kanals 3 marlas including that of the

petitioner to the extent of his 1/6th share situated in village Dogri

within the municipal limits of Jalandhar City is sought to be acquired

for the construction of 132 KV Sub Station in village Kahanpur

[Village Dogri] by the Punjab State Electricity Board.

Earlier also, the aforementioned land was acquired by the

respondents for the same ‘public purpose’ vide notifications dated

6.4.2000 and 15.6.2001 issued under Sections 4 and 6 of the Act

respectively. The said acquisition proceedings came to be

challenged by the petitioner along with his brother by way of CWP

No. 12194 of 2001 which was allowed by a Division Bench of this

Court vide judgment dated 11.9.2003 [Annexure P-2]. Suffice it to
CWP No. 6015 of 2005. ::-2-::

say that after taking judicial notice of the deliberate “actions and

omissions” on the part of the public officers which frustrated the

acquisition process meant for an important public purpose, this

Court arrived at the conclusion that the award was not passed within

the stipulated period of two years as provided under Section 11-A of

the Act. The Bench further held as under:-

“In the result, the writ petition is allowed. Notifications
dated 6.4.2000 and 15.6.2000 are declared illegal and
quashed. However, keeping in view the fact that the land
of the petitioners was being acquired for a large public
good, we deem it proper to observe that the State
Government shall be absolutely free to re-initiate the
proceedings for acquisition of the land. We also direct the
State Government to initiate disciplinary action against
the Land Acquisition Collector who was responsible for
not pronouncing the award within the prescribed time limit
and submit a report to this Court within six months after
completing the disciplinary proceedings. It will also be
appreciated if the State Government issues written
instructions to all the Land Acquisition Collectors that
they must pronounce the award within the time limit
prescribed under the Act and their failure to do so would
necessarily result in initiation of departmental enquiry for
major penalty”.

It was thereafter that fresh acquisition process was

initiated by issuing the notification dated 25.2.2004 under Section 4

of the Act [Annexure P-1]. The petitioner submitted his objections

under Section 5-A of the Act, inter-alia, pointing out that [i] the

alleged public purpose for which the land is sought to be acquired

has already been successfully achieved by installing 132 KV Sub

Station at village Alawalpuri; [ii] the Senior Engineers of the Board
CWP No. 6015 of 2005. ::-3-::

are of the view that the subject land is no longer required for

establishing a power Sub Station; [iii] the acquired land is an Orchard

where plants of Mango, Orange, Lemon of grown-up age are

standing and no useful purpose will be served by acquiring such

land; [iv] all Sub Stations have been established on a piece of land

measuring not more than one or one and half acres, therefore, the

entire land of the petitioner is not required for the alleged public

purpose.

The objections having not found favour with the State

Government and on the issuance of the resultant notification under

Section 6 of the Act, that the petitioner has again approached this

Court.

Respondents No. 2 and 3, i.e., Punjab State Electricity

Board and its authorities have filed their counter-affidavit. Thereafter,

an additional affidavit dated 27.11.2008 has also been filed by the

Land Acquisition Collector, PSEB, Patiala. The reconstructed records

[original is reported to have been lost] of the office of the Land

Acquisition Collector as well as of the State Government have also

been produced and perused.

Learned counsel for the parties have been heard at some

length.

It is argued on behalf of the petitioner that the entire

acquisition process is vitiated in law for the reason that the

petitioner’s objections have not been dealt with or disposed of in

accordance with the mandatory procedure laid down under Section

5-A of the Act. It is urged that the petitioner was served with a notice
CWP No. 6015 of 2005. ::-4-::

to appear in person on 10.8.2004 by the Land Acquisition Collector

and on submission of additional objections in writing on his behalf by

his counsel on that day, the matter was adjourned to enable the

PSEB authorities to submit their comments on those additional

objections. Thereafter, no opportunity of being heard was ever given

to the petitioner and the objections were sent by the LAC to the State

Government for appropriate decision. Relying upon the order dated

10.8.2004 [Annexure P-4] and the communication dated 8.2.2005

[Annexure P-7], it is contended that the objections submitted by the

petitioner have been rejected by the State Government without there

being any report from the Collector u/s 5A of the Act. To be precise,

it is urged that while the Collector failed to afford an opportunity of

being heard, the objections have been turned down by the Authority

who did not even call for hearing. It is strenuously urged that the

duties of the Land Acquisition Collector under Section 5A are of

quasi-judicial nature and not an empty formality and right of hearing

under Section 5A is akin to fundamental rights as the only

opportunity of being heard before acquisition of one’s land is

envisaged by the said provision. In support of this contention, learned

counsel has relied upon a judgment of this Court Gopal Krishan

Gupta & Ors. V State of Haryana & Ors., 1993 PLJ, 603.

It is then argued that the Board’s own experts, namely,

Additional Superintending Engineer vide his memo dated 9.11.2004

[Annexure P-5] has categorically opined that there is no necessity to

construct the Sub Station at the proposed site. Reference is then

made to a communication dated 9.8.2005 [Annexure P-13] by the
CWP No. 6015 of 2005. ::-5-::

Chief Engineer [Operations] to the Member [Distribution], PSEB,

Patiala wherein also he has elaborately dealt with the issue of

construction of the proposed Sub Station and then recommended

that “there is no need of the proposed 132 KV Sub Station at

Kahanpur [Dogri]”. Reliance is also placed upon another letter dated

11.11.2005 [Annexure P-14] by the Engineer-in-Chief , Sub Stations,

PSEB informing the Secretary of the Board that there is no need of

the proposed 132 KV Sub Station at Dogri and intimation to this

effect may be sent to the LAC of the Board. The petitioner’s case

appears to be that notwithstanding the recommendations made by

the Senior Engineer of the Board for not acquiring the land, some

officers/higher authorities in the Board, on account of their personal

vendetta, were hellbent to acquire the petitioner’s land and it was

with that ulterior motive that Memo dated 19.12.2005 [Annexure P-

15] was sent to the Additional Superintending Engineer to give his

second opinion as to whether or not the subject land was required for

construction of 132 KV Sub Station at Kahanpur [Dogri], more so

when there were no directions issued by the High Court as wrongly

mentioned in the said letter. Alternatively, it is maintained that all the

Sub Stations have been constructed over land measuring not more

than one or one and half acres whereas the petitioner and his

family’s land measuring more than three acres is sought to be

acquired.

On the other hand, learned counsel for the respondents

have argued that the Competent Authority to take the final decision

as to whether or not the subject land is required for the construction
CWP No. 6015 of 2005. ::-6-::

of the proposed Sub Station is the Secretary and the Chairman of the

Board and not the Engineer-in-Chief or so. It is pointed out that the

recommendations made by the Senior Engineers of the Board in

favour of the petitioner were duly considered by the Competent

Authority but the same did not find favour as the Board had taken a

conscious decision to construct 132 KV Sub Station at Kahanpur

[Dogri] in order to meet the increasing demand of power supply to the

Industries growing in the adjoining areas. Relying upon the records

of the Land Acquisition Collector, it is argued that an opportunity of

being heard was duly afforded to the petitioner who put in

appearance through his counsel. Reference to the notings from the

Government file has also been made in order to show that there was

due application of mind and a conscious decision has been taken as

to why the subject land should be acquired for construction of the

Sub-Station in question. On this premise, learned counsel submitted

that the procedure envisaged by Section 5-A of the Act has been

faithfully complied with.

It is then argued that even if there are no specific

recommendations, either way, by the Collector, the State

Government is not precluded from taking a decision regarding

acquisition of a land. Reference has been made to the judgment of

this Court in Dharam Pal & Anr. V State of Haryana, 2007[4] PLR,

299. Reliance is also placed upon the judgment in Scindia

Employees’ Union v State of Maharashtra & Ors. [1996] 10 SCC,

150 to contend that the scope of inquiry under Section 5-A of the Act

pertains to as to whether the land sought to be acquired is needed
CWP No. 6015 of 2005. ::-7-::

for a public purpose or not.

Having heard learned counsel for the parties, I do not find

any merit in this writ petition. There is no gain in saying that Section

5-A[2] of the Act contemplates observance of natural justice and a

fair procedure by giving an opportunity to the landowners to submit

their objections in writing and then an opportunity of being heard in

person or through a representative or by pleader on such objections.

If the situation so permits, the Collector can hold a further inquiry and

then submit his report/recommendations together with the records of

the proceedings to the State Government, who being the Competent

Authority is required to take a final decision on such objections. It is

true that the procedure provided under Section 5A[2] is not an empty

formality nor the role of the Land Acquisition Collector is that of a

postal authority to receive the objections and pass-on to the State

Government. At the same time, the Collector does not enjoy upon

any adjudicatory powers under sub-Section [2] and he is just to send

his recommendations to the State Government, as held by the

Hon’ble Supreme Court, on the limited issue as to whether or not the

land proposed to be acquired is required for the public purpose. It is

not in dispute that there was a difference of opinion amongst the

Engineers of the Board as to whether or not 132 KV Sub Station is

required to be constructed in Kahanpur [Dogri]. In deed, the record

does suggest that the State Government rejected the objections of

the petitioner under Section 5-A of the Act after accepting the opinion

of the Engineers to the effect that the Sub Station was required to be

constructed and a communication to this effect was sent to the
CWP No. 6015 of 2005. ::-8-::

petitioner also vide Annexure P-7, followed by the notification under

Section 6 of the Act. It further appears that after the issuance of

notification under Section 6, some of the Engineers working in the

Board recommended that there was no necessity to construct the

Sub Station at the acquired land. Their recommendations were again

considered by the State Government which took a conscious

decision, agreeing with the Secretary/Chairman of the Board that the

Sub-Station in question is required to be constructed.

The construction of a power Sub Station entails huge

expenditure. Its corresponding utility for the public purpose sought to

be achieved, is also to be kept in view. In such like matters,

difference of opinion amongst the functionaries of the acquiring

department is neither unusual nor unexpected. While exercising the

powers of judicial review, this Court would be well within its right to

see as to whether the divergent views have been accepted or

rejected mechanically and/or there is a due application of mind by the

Competent Authority. If one goes through the contents of the

decision taken by the State Government second time, it is manifest

that the decision to construct the Sub-Station has been taken after

due deliberations and not in a casual fashion and/or to deprive the

petitioner of his land.

Adverting to the next contention that after the construction

of a Power Sub-Station at Alawalpur, there is no need to construct

the present Sub-Station, suffice it to say that such like decisions fall

within the domain of the experts and are beyond the scope of judicial

review. The necessity of a public utility is to be seen mainly by the
CWP No. 6015 of 2005. ::-9-::

State Government or the Board. Both of them have taken a

categoric stand that the Sub-Station is required to be constructed at

the site. It has also been explained that some new industrial units

have been set up in the vicinity and there is a growing demand for

power supply. It is to facilitate the additional demand for the power

supply that a new Sub-Station is required to be constructed at the

site in question. There is nothing on record to suggest that the

respondents would not utilize the land for construction of a Sub-

Station inasmuch as they have got no opportunity to raise the

construction till date as dispossession of the petitioner remained

stayed under the orders of this Court.

Similarly, the contentions that there are some fruit plants

standing over the land or that a lesser area could serve the public

purpose also merit rejection. The award passed by the Land

Acquisition Collector suggests that a compensation of Rs.1170/- has

been granted towards the value of the fruit trees which leaves no

manner of doubt that these were newly planted trees only. So far as

achieving of the public purpose by acquiring a smaller piece of land

is concerned, the respondents have come up with a categoric stand

that the entire land is required not only for the present purpose but

for its future expansion also.

For the reasons aforementioned, I do not find any merit in

this writ petition which is accordingly dismissed, however, leaving the

parties to bear their own costs.


December 15, 2008.                        ( SURYA KANT )
dinesh                                        JUDGE